Råmmarehemmet wind farm

EnBW Sverige AB is constructing its first wind farm in Sweden in Råmmarehemmet in the district of Tidaholm. It will consist of three wind turbines with a total output of around 11 megawatts and is due to be placed into operation by summer of 2021.

Wind farm

Project details

Locations of the turbines at the Råmmarehemmet wind farm
Locations of the turbines at the Råmmarehemmet wind farm

Wind conditions

Consideration for people and the environment

Connection to the grid

Latest news

March 2021
During calendar week 10, tower segments and rotor blades for wind turbines two and three will be transported to Råmmarehemmet. The construction of the two turbines is planned to start towards the end of the week. Please respect that entering the construction site is not allowed due to the risk of accidents. If you wish to visit the site, please register for an approval by the site management.

February 2021
From calendar week 7, the establishment of cranes will begin. During calendar weeks 8 and 9, office- and storage modules will be brought up on the construction site. Next in line are transports of other building parts before the nacelle and rotor blades arrive. According to project manager Johnny Andersson at EnBW, large heavy parts will preferably be transported at night to avoid traffic disruptions as much as possible.

December 2020
The foundations are now complete and Råmmarehemmet's construction site will take its Christmas break from calendar week 52. Minor adjustments and remaining work will then be made during January-February 2021. The heavy transports to the foundations have meant the project's greatest traffic load. Starting at the end of February and the beginning of March, the establishment of cranes and other equipment will begin, and immediately thereafter the components of the wind turbines will be delivered. Transports with a large impact on road accessibility are planned to be carried out preferably at night when the traffic intensity is low. We will of course provide new information as soon as there are more exact dates. Everyone in the project team wishes our neighbors a Merry Christmas and a Happy New Year 2021!

October 2020
The first and southernmost of the new foundations was completed in calendar week 41. At the moment, we are working with the probations of the other two foundations. Foundation number 2 will be poured according to plan on Thursday 15 November. The third and last foundation will then be ready in calendar week 43, more precisely on Tuesday 20 October. On these days, residents must expect increased traffic congestion.

August 2020
Please respect that entering the construction site is not allowed due to the risk of accidents. If you wish to visit the construction site, you will only do so after registration and approval by the site manager Henric Wass / PEAB: +46 733 373729

July 2020
Construction work on the wind farm was resumed. Currently, we are removing the old foundations. As soon as next steps are taken, we will inform you.

{{global.get('MSG_FOOTER_BACK_TO_TOP_BUTTON_LABEL')}}