Green light for EnBW He Dreiht offshore wind farm

Download image
Symbolic image of the EnBW offshore wind farm Hohe See (Image source EnBW / photographer Rolf Otzipka)

Final investment decision made / 960-megawatt major project to be realized without state subsidies as one of the world’s first zero-cent bids in an offshore auction / Investment volume of approximately €2.4 billion / Consortium consisting of Allianz Capital Partners, AIP and Norges Bank Investment Management acquires 49.9%.

Download image

Yesterday's final investment decision clears the way for the start of construction of EnBW’s largest offshore wind farm to date, with an installed capacity of 960 megawatts (MW). “The final investment decision for the construction of our He Dreiht offshore wind farm is an important milestone in accelerating the energy transition. Long planning horizons and extensive preparatory work in the offshore wind industry require a high degree of foresight, expertise and readiness to make decisions and invest. This is another big step towards a carbon-free energy future,” said EnBW CEO Andreas Schell.

EnBW CFO Thomas Kusterer said: “In He Dreiht, we are building one of Germany’s largest offshore wind farms. We succeeded in the first German offshore tender in 2017 with a zero-cent bid and made an important contribution to the further development of the offshore market.” Kusterer added that yesterday’s decision is the reward for more than six years of outstanding teamwork. A combination of factors made the zero-cent bid possible. These include the installation of the latest wind turbine technology, synergies with existing sites and long-term power purchase agreements with industrial customers, which have a stabilizing effect on wind farm revenues.

Download image

This subsidy-free offshore wind farm is currently one of the largest energy transition projects in Europe. The investment cost for He Dreiht is around €2.4 billion. It is expected to be operational by the end of 2025. He Dreiht will then generate green electricity for the equivalent of 1.1 million households.

“With the sale of a 49.9% minority stake to a consortium consisting of Allianz Capital Partners on behalf of Allianz insurance companies, AIP and Norges Bank Investment Management, we have succeeded in bringing highly professional and experienced partners on board even before construction begins,” said CFO Thomas Kusterer.

EnBW has so far signed several long-term power purchase agreements (PPAs) for He Dreiht with well-known companies such as Fraport, Evonik, Salzgitter and Bosch, covering a total volume of 335 MW. Talks with other companies are underway.

In the expansion of renewables, PPAs are an important means of underpinning and financing unsubsidized projects in the market. At the same time, more and more companies are striving to become carbon neutral, creating growing demand for green, carbon-free power. By entering into PPAs, companies and municipal utilities gain access to green power to meet their own climate targets and serve their customers.

To finance this major project, EnBW has secured an additional €600 million in long-term funding from the European Investment Bank, one of the world's largest financiers of climate and environmental projects.

Download image
Supervisory Board clears the way for construction of the 960 MW wind farm 'He Dreiht' in the North Sea (Site plan image)
960 MW EnBW offshore wind farm in the German North Sea

Located approximately 85 kilometers northwest of the island of Borkum and approximately 110 kilometers west of Heligoland, the He Dreiht wind farm is expected to be operational by the end of 2025. Upon completion, EnBW will be responsible for technical and commercial management as well as maintenance and repair.

EnBW’s existing offshore wind farms Hohe See and Albatros are located nearby. He Dreiht will benefit from this proximity and from the service hub already established in the coastal town of Emden.The plan is for the installation of 64 latest-generation Vestas wind turbines. Introduced to the market as the first 15 MW wind turbine, these are among the most powerful in operation today. They give He Dreiht a total installed generating capacity of 960 MW. This means that the 900 MW grid connection capacity guaranteed for He Dreiht can be fully utilized. EnBW received the plan approval decision and thus the permit for the He Dreiht offshore wind farm from the German Federal Maritime and Hydrographic Agency (BSH) in December 2022.

About EnBW

With over 26,000 employees, EnBW is one of the largest energy companies in Germany and Europe. It supplies around 5.5 million customers with electricity, gas, water as well as services and products in the areas of infrastructure and energy. The expansion of renewable energies is a cornerstone of the growth strategy and a focus of investment. EnBW will invest around 4 billion euros in the further expansion of wind and solar energy by 2025. By the end of 2025, more than half of the generation portfolio is set to consist of renewable energies. This is already having a noticeable effect on reducing CO₂ emissions, which EnBW aims to halve by 2030. EnBW is aiming for climate neutrality by 2035.

Accept Decline Download now Download

Downloads

Contact

Fax: Mobile: Phone:
Fax: Mobile: Phone:
Martina Evers
Group Spokesperson
Fax: Mobile: Phone:
Ramona Sallein
Press Spokesperson
Photovoltaic
Show video
Show YouTube video?

Please note the privacy policy of YouTube.

Related News