In Råmmarehemmet in Tidaholm municipality, EnBW Sverige AB has built its first greenfield wind farm from scratch. It consists of three wind turbines with a hub height of 111 m and a total height of 180 m on site. The total output of around 12,6 megawatts. The wind farm is placed into operation during July 2021.
Project diary
We will keep you informed about important events and milestones during the construction of the Råmmarehemmet wind farm here. You will find the latest information on the planning and approval process here, as well as information about the progress of the construction work:
Wind measurements
|
May 2010 to June 2012
|
Approval for construction received
|
September 2016
|
Acquisition of the project from Contellus Råmmarehemmet AB
|
July 2018
|
Start of preliminary work to prepare for construction
|
September 2018
|
Demolition of old foundations
|
End of June to September 2020
|
Pouring new foundations
|
September to December 2020
|
Anticipated commissioning date
|
Summer 2021
|
June 2021
Now all three wind turbines are fully assembled. They have a hub height of 111 meters and a total height of 180 meters. The rotor diameter is 138 meters. Each of the three turbines has a nominal power of 4.2 MW. Thus, Råmmarehemmet can cover the annual electricity needs for approximately 9,500 households with an average annual consumption of 4,000 kWh. The wind farm is connected to the local energy company Tidaholm Energi's grid.
Contact
Diary
December 2018: The access route to the WTG 2 site has been started.
January 2019: The area where the crane will be erected for the WTG 2 site is being prepared.
February 2019: Completation of the crane parking area
February 2019: Finalisation of the foundation area
February 2019: Expansion of the access route
March 2019: Fabrication of the foundation has been started
April 2019: Fabrication of the foundation is completed
Juli 2020: Work has restarted on the wind farm after an enforced break lasting one year. The old foundations are currently being demolished.
September 2020: After demolishing the old foundations, the new foundations are now being cast.
December 2020: Work on the foundations has been completed. The cranes are now being assembled and this will be followed by the delivery of the wind power plants.
February 2021: The Substation has been delivered. Now the assembly is about to start.
March 2021: The assembly of the tower has started and the first component has been installed.
April 2021: The first wind power plant was assembled with the blades.