Close Download image Share
EnBW Baltic 2 wind farm

The 80 large wind turbines at EnBW Baltic 2 rise high above the waves of the Baltic Sea. The second EnBW wind farm was officially placed into operation on 21 September 2015. The turbines use the powerful and constantly blowing wind to generate electricity for an aggregate of 340,000 households.

Download image

Baltic 2 technology

Building 80 wind turbines and a substation and connecting the entire 27 km² area with around 85 km of submarine cables requires precise planning. All individual processes must be precisely coordinated: The cables can only be laid within the wind farm once the foundations have been completed. Then the wind turbines are built. The substation must be completed in good time before the wind farm’s cables are laid and the first turbine built.

Download image

Our site managers and logistics specialists can expect challenging tasks, such as estimating the working speeds, calculating the transport routes – and coordinating everything with the weather conditions.

One single ship for the wind turbines, up to two ships for the foundation structures and up to three ships for connecting the cables travel from different ports and arrive at the construction site at different times. The site is further secured by a sea traffic management vessel.

The sea is a capricious project partner: It must not be too cold, otherwise the special cement used to join the foundation components will not set.

The transformer platform needs calm seas to reach its destination and set itself up. The wind turbines can only be installed at wind speeds of up to force 4–5.

For each construction phase, all components not only have to be transported to and installed at the site, which lies 32 km off the German coast, but the crews also need to be regularly replaced.

Even though it only takes around two hours for the crew transfer ships to sail to the construction site from our base port in Sassnitz, a heavy installation platform can take up to 12 hours to get there. As such, it is essential to think of everything – because every delay can cost a six-figure sum each day.

Logistics and coordination

Download image

The same white chalk in the famous chalk cliffs of Rügen can be found in the Baltic Sea. On top of this is the so-called boulder clay, a layer of sediment that formed during the melting of the Ice Age glaciers. The foundations are driven between 36 and 55 meters into the ground in order to ensure that they are securely anchored.

Each foundation must be individually adapted to different sea depths ranging from 23 to 44 meters. Monopiles up to 35 meters long are used, depending on the water depth. From a depth of 35 meters, three-legged jackets are used.

The monopiles and the foundation piles for the jackets are driven into the seabed using a pile driver aboard a special ship. The so-called transition pieces, which connect the foundation to the tower, are then placed over the monopiles like a cuff and firmly joined using a special cement.

For the three-legged jackets, the position of the foundation piles is precisely determined by large templates on the seabed.

Only then are the jackets set on the piles and firmly joined using a special cement. It can take up to five days to install a foundation, depending on weather conditions.

The foundations

Download image

The components are manufactured at various locations in Denmark and delivered to Mukran Port in Sassnitz, where we are based. Here, the steel towers, nacelles and rotor blades are stored on an area covering 80,000 square meters and pre-assembled two to three months before installation begins.

Components for several turbines can be towed to the construction site on a floating assembly platform. In order to lift the enormous weights, the platform stands on legs firmly secured on the seabed and rises about 10–15 meters above the water level. Each turbine is installed from this platform in around 36 hours.

The steel towers, which weigh 256 metric tons and are around 66 meters tall, are placed on the foundations using a crane and bolted together. The nacelle, which weighs around 150 metric tons, is mounted with the generator and the gears. Finally, the individual rotor blades are installed.

.

Wind turbines and construction

Download image

Measuring 40 x 40 meters wide and 14 meters high and weighing 4,400 tons, the transformer platform floats on its own. Besides saving transport costs, the installation of the platform is also less complex: It brings the upper section of its foundations with it in an inwardly retracted state and can therefore base itself on the preinstalled lower section.

Firstly, tugboats tow the transformer platform from the shipyard to the construction site. Once in position, it lowers its jacket foundation structure and lifts itself up about one meter above sea level. Only the substructure on which the jacket structure sits must firstly be anchored to the seabed using foundation piles.

The electricity from the 80 wind turbines flows into the substation and is transformed from a voltage of 33 kV to 150 kV. A low voltage requires a very thick cable to transport electricity in order to prevent transmission losses.

To avoid having to lay such a cable underwater for several kilometers, the electricity is transformed as close as possible to the generation source, which is why the transformer platform is installed at the wind farm on the high seas rather than on land.

Transformer platform and installation

Download image

The wind farm’s internal power grid is around 85 kilometers long. The cables are transported to the construction site directly from Norway.

Besides transporting the electricity, the 11.9- and 14-centimeter-thick submarine cables also transmit information and data between the turbines and the control room in Barhöft via highly sensitive optical fibers that are integrated into the cables.

The so-called export cable transports the electricity from the substation via EnBW Baltic 1 to the nearest substation on land. Here, at Bentwisch substation, the voltage is once again transformed from 150 kV to 380 kV and fed into the German grid by 50Hertz Transmission GmbH.

Wind farm cabling and grid connection