Back to top Close Light Download image Go to slide [COUNT] Dark Next slide Previous slide Scroll left Scroll right Reset search input Submit search Share Stock exchange is momentarily closed

Walheim sewage sludge combined heat and power plant

Project diary

Download image

This is where we inform you about important events and milestones relating to the planning and construction of a sewage sludge combined heat and power plant on the Walheim site. You will find the latest information here on the timetable for the planning and permit process as well as the progress of the construction work.

Provisionally 2027
Start-up phase and commercial commissioning
Provisionally 2026
Installation of plant technology
Provisionally Q2 2025
Shell construction work
February 2025
Bored piles for the foundations
October 2024
Approval for advance construction work to begin
November 2023
Completion of documentation for the approval application
March 2023
Approval application checked by the authorities to ensure it is complete
February 2023
Approval application submitted
26 October 2022
Scoping meeting* held by Stuttgart Regional Council
Start of 2022
Dialogue with the municipality
2020/2021
Early public consultation process, presentation to the Municipal Council, expert reports produced

* In complex planning processes, a scoping meeting is held by the authority overseeing the process (in this case Stuttgart Regional Council). With the involvement of public agencies and specialist authorities, the meeting is used to formally determine the subject, scope and methodology of the regional impact and environmental impact studies as well as the content of the application documents that need to be drawn up.

less more

Construction diary

January 2024: The public review of the application documents begins

On 23 February 2023, EnBW submitted an application to Stuttgart Regional Council (RPS) as the licensing authority for the issuance of the first partial permit under immission control regulations for the construction and operation of the sewage sludge combined heat and power plant planned on the Walheim site.

RPS then went through the application documents to check that they were complete. The checks revealed that certain elements still needed to be added to the application. These were then requested and later supplied by EnBW. The licensing authority confirmed that the submitted application documents were now complete, allowing the approval process to enter the next phase.

On 19 January 2024, the project was publicly announced in the “Staatsanzeiger” and on the websites of RPS and the municipalities of Walheim and Gemmrigheim as well as on the central website www.uvp-verbund.de/bw. The announcement text can be found on the RPS website at www.rp-stuttgart.de > Service > Announcements > Environmental matters.

The public review of the application documents was held in the municipality of Walheim, the municipality of Gemmrigheim and the RPS offices from Friday, 26 January up to and including Monday, 26 February 2024. The documents could be viewed at the following locations during the respective opening hours of the offices:

  • Walheim Town Hall, Hauptstraße 68, 74399 Walheim, Room 12
  • Gemmrigheim Town Hall, Ottmarsheimer Str. 1, 74376 Gemmrigheim, Building Authority, Room 12
  • Stuttgart Regional Council, Ruppmannstr. 21, 70565 Stuttgart, Room B 1081

Parallel to the review of the application documents, documents relevant to the decision-making process were posted on the environmental impact assessment website: www.uvp-verbund.de/bw

Objections to the project could be raised in writing to RPS or the municipalities of Walheim and Gemmrigheim at the aforementioned addresses or electronically by e-mail to from Friday, 26 January up to and including Tuesday, 26 March 2024. The name and full address of the person raising the objection had to be stated and the letter had to be signed. Objections had to at least indicate the suspected threat to legal interests and the nature of the negative impact.

Parallel to the announcement and the review of the application documents, RPS asked the bodies representing the public interest affected by the plans for an expert opinion on the project. The meeting to discuss the planned sewage sludge combined heat and power plant in Walheim was set for Monday, 24 June 2024, at the Forum in Ludwigsburg, in the event of any objections having been raised in the context of the immission control procedure.

News, Dates & Contact
Dates

No dates are currently scheduled.

Contact

Do you have questions about the project? We are here for you! Contact us by e-mail at any time.

E-Mail: