Project diary for the Weesow-Willmersdorf solar park
General development planning with an amendment to the land-use plan and preparation/legal validity of the development plan
|
2009 / 2010
|
1st amendment to the development plan (extension of the service life until 2060)
|
2017 / 2018
|
Acquisition of the project company by EnBW Solar GmbH
|
July 2018
|
Building application submitted
|
April 2019
|
Building permit received for the Weesow-Willmersdorf solar park
|
August 2019
|
Public consultation for citizens
|
28 November 2019
|
Preliminary work to prepare for construction
|
December 2019
|
Construction phase for the Weesow-Willmersdorf solar park
|
2020
|
Commissioning of the Weesow-Willmersdorf solar park
|
End of 2020
|