North of the city of Werneuchen in the Barnim region of Brandenburg, EnBW Energie Baden-Württemberg AG is planning to construct a solar park with an output of more than 187 MW. The solar project will be the first major PV project to be realised without any EEG subsidies.
Project diary for the Weesow-Willmersdorf solar park
We will keep you informed about important events and milestones during the construction of the Weesow-Willmersdorf solar park here. You will find the latest information on the planning and approval process, as well as information on the progress of the construction work:
General development planning with an amendment to the land-use plan and preparation/legal validity of the development plan
|
2009 / 2010
|
1st amendment to the development plan (extension of the service life until 2060)
|
2017 / 2018
|
Acquisition of the project company by EnBW Solar GmbH
|
July 2018
|
Building application submitted
|
April 2019
|
Building permit received for the Weesow-Willmersdorf solar park
|
August 2019
|
Public consultation for citizens
|
28 November 2019
|
Preliminary work to prepare for construction
|
December 2019
|
Construction phase for the Weesow-Willmersdorf solar park
|
2020
|
Commissioning of the Weesow-Willmersdorf solar park
|
End of 2020
|