Project diary for the Weesow-Willmersdorf solar park

General development planning with an amendment to the land-use plan and preparation/legal validity of the development plan
2009 / 2010
1st amendment to the development plan (extension of the service life until 2060)
2017 / 2018
Acquisition of the project company by EnBW Solar GmbH
July 2018
Building application submitted
April 2019
Building permit received for the Weesow-Willmersdorf solar park
August 2019
Public consultation for citizens
28 November 2019
Preliminary work to prepare for construction
December 2019
Construction phase for the Weesow-Willmersdorf solar park
2020
Commissioning of the Weesow-Willmersdorf solar park
End of 2020
{{global.get('MSG_FOOTER_BACK_TO_TOP_BUTTON_LABEL')}}

Why do we use cookies and pixels?

To make your visit as convenient as possible. For this purpose, we use cookies on our website, which are technically necessary for the site operation, as well as technologies for anonymised statistical production.

With your consent, we would like to use additional cookies and pixels that allow us to display targeted information and content. We will pass your data on to third parties for this reason. For details on the technologies used, information on their revocation options or information on data transfer to third parties, please refer to our privacy policy.

If you click on "Decline", only those cookies that are technically necessary will be stored on your computer. If you click on "Agree and continue", you consent to the usage of all cookies.

Privacy Policy | Legal Notice