Back to top Close Light Download image Go to slide [COUNT] Dark Next slide Previous slide Scroll left Scroll right Reset search input Submit search Share Stock exchange is momentarily closed

Marbach grid stabilization plant

Download image

In order to guarantee grid stability and security of supply, additional generating plants (“special technical equipment pursuant to Section 11(3) EnWG”) are needed as part of the energy transition. EnBW has built such a grid stabilization plant at its power plant site in Marbach am Necker. The plant has been in operation since end of September 2024.

Grid stabilization plant

Download image

Project introduction

An important milestone for securing the electricity supply in Germany has been reached: On 30 September 2024, EnBW handed over the new grid stabilization plant on the Marbach power plant site to its client, the transmission system operator TransnetBW. This plant will keep the nationwide power grid stable in the event of any equipment failure. Its use is regulated by law and it may only be put into operation by TransnetBW on demand.

Due to Germany’s phasing out of nuclear power and the increased use of renewable energy sources, it is necessary to expand the German electricity grid. Not least because the electricity generated mainly in the north from renewable sources must also be transported to southern Germany. This grid expansion is only progressing slowly, which means that additional reserve capacity is needed to ensure grid stability.

The Federal Network Agency had therefore decided to have new generating plants built in southern Germany in addition to the existing power plant stock. These grid stabilization plants are only used if one or more plants within the power grid have already failed and there is a specific threat to grid stability. In such cases, the grid stabilization plants serve to ease the load on the power grids on a short-term basis.

The transmission system operators TransnetBW, Amprion and TenneT defined the capacity they each require and issued invitations to tender for the construction of suitable power plants within their control zones to cover this capacity. TransnetBW GmbH has issued an invitation to tender for a capacity of 300 megawatts (MW) for Baden-Württemberg.

EnBW had participated in this tendering process with its Marbach am Neckar power plant site. Having secured the contract in August 2019, a so-called open-cycle gas turbine was then installed there. The advantage of such turbines is their ability to supply a high level of electrical power within a relatively short space of time. Following the completion of the construction phase, the plant has now been in operation since end of September 2024.

Download image
Time lapse from construction to completion of the Marbach grid stability plant.
Download image
This diagram shows how the new grid stabilization plant works.
Download image

Technology

The grid stabilization plant essentially consists of a gas turbine with filter house for air intake, a diffuser for drawing off the hot exhaust gases from the turbine into the separate chimney, a generator and the associated ancillary and auxiliary systems. Occupying a total area of around 14,000 square meters, the plant is located on the existing company site at Thomas-Alva-Edison-Ring.

  • The compressor draws in air and compresses it.
  • The oil-water emulsified fuel is injected into the combustion chamber and ignited.
  • The hot combustion gases drive the turbine.
  • The turbine drives the generator, with part of the energy used to compress the intake air.

The gas turbine is fired with light fuel oil. This will avoid any potential difficulties in obtaining the fuel supply to the greatest possible extent. That’s because the large oil storage facility on the power plant site (with a total capacity of approx. 70,000 m³) ensures that the fuel is available all year round. This is especially important in winter, because any threat to grid stability is most likely to occur during cold periods.

Specifications

Download image

The plant has been built as an open-cycle gas turbine powered by extra-light fuel oil (LFO). It has a thermal output of 940 MW and an electrical output of 300 MW.

Operation mode
Full load
Max. thermal output
940 MW
Electrical efficiency
>33 %
Electrical output
300 MW
Max. operating hours at full load
500 h/a
Time to full load
30 min
Fuel
Extra-light heating oil (standard)
Heating value
42,6 MJ/kg
Mass flow rate of fuel
79.449 kg/h
Show video
Show YouTube video?

Please note the privacy policy of YouTube.

"What is a grid stability system?" explained simply.

Approach

Download image

Project phases

This is where we inform you about important events and milestones relating to the planning and construction of the grid stabilization plant on the Marbach site. You will find the latest information here on the timetable for the planning and approval process as well as the progress of the construction work.

End of September 2024
Commercial operation of the grid stabilization plant
Q4 2023
Work starts on commissioning the grid stabilization plant
July 2022
Commissioning of demineralization plant
April 2022
Grid connection completed
December 2021
Approval change
July 2020
Approval granted and start of construction
3rd quarter 2019
Start of work on existing 110 kV plant at the site
3rd quarter 2019
Application submitted for approval in line with immission control regulations
August 2019
Contract awarded to EnBW upon completion of the tendering process
December 2018
Scoping meeting* for Stuttgart Regional Council
29 November 2018
Citizen information
Energy and technology park at Marbach power plant
Reinhold-Würth-Straße 4 / Am alten Kraftwerk, first floor

* In complex planning processes, a scoping meeting is held by the authority overseeing the process (in this case Stuttgart Regional Council). With the involvement of public agencies and specialist authorities, the meeting is used to formally determine the subject, scope and methodology of the regional impact and environmental impact studies as well as the content of the application documents that need to be drawn up.

Construction diary

Frequently asked questions

Download image

The power grid can only be stably operated if the energy generated corresponds to the energy consumed at any given moment. A change in consumption must be instantly balanced on the generation side, which is why power plants have balancing reserves and quickly controllable power plants can balance this change in consumption at short notice.

Fluctuating generation from renewable energy sources (such as photovoltaics or wind power) must also be balanced by conventional power plants, nuclear power plants or pumped-storage power plants.

How is the power grid kept stable?
Download image

Even if certain equipment (i.e., a system such as a switch, a power line or a transformer) fails, the power grid can still be operated in a stable manner. This is known as (n-1) security. The remaining lines/systems then take on the task of transmitting the electricity. The circuits are usually not overloaded, meaning that the failure is safely controlled – as long as no further equipment fails during this phase. That is why so-called (n-1) security must be restored as soon as possible. This is achieved by easing the load on the power grid locally through generation capacity that can be activated quickly.

In the past, power grids were rarely operated at the limits of (n-1) security because the transmission distances were significantly shorter than they are today due to power being generated close to where it was consumed. Even after the failure of equipment, (n-1) security was often still guaranteed – helped by the grid’s normally unused overload capacity in those days. Today, the grids are increasingly being operated at their technical limits. As a result, the number of interventions required to ease the pressure on the grid has increased significantly in recent years.

How is security of supply guaranteed?
Download image

The situation on the generation side will change significantly in the future due to the following factors:

  • The phaseout of nuclear power
  • Further expansion of renewable energy capacity increasingly leading to a generation surplus in northern Germany, which has to be redirected toward southern Germany
  • Delayed grid expansion of high-voltage lines between northern and southern Germany

These factors are having a particularly serious impact in southern Germany. Additional generation plants are therefore needed to guarantee grid stability and security of supply. However, these will not be used to compensate for the lost capacity previously provided by nuclear power plants, but will only be used for a relatively brief length of time to support the power grids in the event of problems in the transmission grid if equipment fails (see also question 2).

Why are so-called grid stabilization plants needed in southern Germany?
Download image

The capacity of conventional generation plants and pumped-storage plants has been factored into the calculations for new grid stabilization plants when determining the power needed. In an analysis, the Federal Network Agency concluded that an additional 1,200 megawatts (MW) of rapidly accessible generation capacity are needed in southern Germany to guarantee security of supply in the event of a fault in the grid.

Aren’t there already enough conventional generation plants in southern Germany to guarantee grid stability?
Download image

The current reserve power plants are used to balance any power deficiency in the power grid and support grid stability as a preventive measure, even if no equipment within the power grid has failed and the grid remains stable.

The new grid stabilization plants, meanwhile, will only be used if one or more system elements (such as a switch, a power line or a transformer) have actually failed within the transmission grid, placing the power grid in a critical condition. Grid stability will then be restored with the help of these new plants. The grid stabilization plants are also available much more quickly than the existing grid reserve, which is usually made up of older plants.

What is the difference between the existing reserve power plants and the new grid stabilization plants?
Download image

The grid stabilization plant will only be started up in the event of an equipment failure within the transmission grid. In most cases, they are used secondarily to all existing power plants. As such, in our view, a very small number of operating hours can be expected.

However, the operator (in the event of being awarded the contract in the tendering process: EnBW) has no influence on the plant’s use and operating life. This is the responsibility of the transmission system operators, who decide entirely independently how the grid stabilization plant is used.

How often will the plant be started up?
Download image

The operative word “gas” describes the medium that drives the turbine. Steam drives a steam turbine and wind drives a wind turbine. A gas turbine, meanwhile, is driven by hot combustion gas, which is why it is known as a “gas turbine” – regardless of which fuel is used to produce the hot combustion gas.

Why isn’t the gas turbine called an oil turbine if it is fired with oil?
Download image

No, the gas turbine is built as a new block at the Marbach site and will not replace any of the existing plants.

Is the new gas turbine intended to replace the old plants?
Download image

Back in 2013, EnBW applied for the final decommissioning of all generation plants in Marbach. Since the plants have been classified as having system relevance by the transmission system operator since 2013 (most recently in 2018), they have been subject to a decommissioning ban ever since and are started up at the request of the transmission system operator.

The operating license for some of the existing plants (MAR II gas turbine and MAR III boiler and steam turbine) expires at the end of 2023, so we must assume that these plants will be decommissioned at the end of 2023.

What is happening to the existing plants on the site?
Download image

The plant will be kept available for a period of ten years.

What is the planned operating life of the new plant in Marbach?
Download image

The emissions and in particular the gas turbine’s impact on the environment have been examined as part of the immission control approval process. Approval will only be granted if operating the gas turbine has no significant impact.

How much emissions does the plant produce?
Download image

In our view, light fuel oil is more suitable as a fuel than natural gas in Baden-Württemberg. This will avoid any short-term supply bottlenecks, which could occur if natural gas were used. Furthermore, security of supply in southern Germany should not depend on a single primary energy source like natural gas. In conjunction with the large (already existing) oil storage facility in Marbach, we consider light fuel oil to be the ideal fuel for this purpose.

Since the grid stabilization plant is not expected to be used very often, the fuel will have no significant impact on the environment. Gas turbines that run on fuel oil are also subject to much lower emission limits today than they were around 20 years ago.

Why has light fuel oil been chosen for the fuel rather than gas?
Download image

This will be examined and evaluated in the course of the approval process. We currently do not expect there to be any significant impact on water resources.

Will there be any impact on water resources?
Download image

Oil will still be supplied by ship via the Neckar. Due to the low number of expected operating hours, we do not currently expect any significant increase in activity.

How will the oil be delivered?
Download image
  • During operations:
    The impact of the gas turbine power plant on surrounding areas will be examined and evaluated in detail as part of the approval process. Approval will only be granted in accordance with regulations governing emissions if the gas turbine can be operated within the permissible limits.
How noisy will it be?
News, Dates & Contact
Dates

No events are currently planned.

Contact

Do you have questions? We are happy to assist you!

Email:

Corporate Communication

Email:

Downloads

Download Accept Decline Download now
The planned Marbach am Neckar grid stabilization plant