Back to top Chapter-links Chapter-navigation Close Content-navigation Light Days Day Download image Go to slide [COUNT] Hours Hour Dark Main-navigation Minutes Minute Next slide Previous slide Read Article Aloud Pause Reading Resume Reading Scroll left Scroll right Reset search input Submit search Seconds Second Share Stock exchange is momentarily closed Tab-navigation

Obrigheim combined cycle gas turbine plant

Download image

The power plant site in Obrigheim is located between Heidelberg and Heilbronn on the Neckar and has shaped energy generation in Baden-Württemberg for decades. In October 1968, the first commercially used pressurized water reactor in the Federal Republic of Germany was connected to the grid here, generating more than 90 billion kilowatt-hours of electricity until it was shut down in 2005. Work has been ongoing since 2008 to dismantle the nuclear power plant. As things stand, it is expected to be completed in the early 2030s in line with nuclear power legislation. Thanks to the existing infrastructure, traditional power plant sites like Obrigheim offer good conditions for potential energy-related reuse concepts. To this end, a new construction project is currently being examined at the site for flexibly dispatchable power plant capacity: A new combined cycle gas turbine plant could initially be operated using natural gas, before switching to hydrogen at a later date. It will then be able to generate carbon-neutral electricity.

Dismantling Obrigheim nuclear power plant

Information on the dismantling of the former nuclear power plant in Obrigheim can be found here:

Find out more

Project

Download image

Energy industry context

One current reason for reuse concepts is provided by a legislative process initiated by the German government and currently underway – the Electricity Supply Security and Capacity Act (StromVKG). The motivation for this legislative project is the high demand for flexible, dispatchable power plant capacity that complements weather-dependent generation from renewable energies. The German government wants to use StromVKG to create a new nationwide incentive framework for investments and issue invitations to tender for corresponding power plant projects. Subject to an economically attractive funding concept and the structuring of a competitive tendering process by the German government, EnBW is exploring the option of making further investments in hydrogen-ready gas power plants in addition to its existing projects in Stuttgart-Münster, Altbach/Deizisau and Heilbronn. In Obrigheim, a new combined cycle gas turbine plant could initially be operated using natural gas, before switching to hydrogen at a later date. It will then be able to generate carbon-neutral electricity. Other locations besides Obrigheim are also being examined by EnBW for their suitability.

In 2025, renewable energies (RE) such as wind and solar covered almost 58 percent of Germany’s gross electricity generation. These sources are dependent on the weather and tend to fluctuate, however, which is why battery storage systems and hydrogen-ready gas power plants are needed in the synchronous grid of continental Europe. Both technologies complement each other in terms of their strengths and together deliver a reliable and affordable energy supply. While battery storage systems are mainly used to cover times of peak demand in the short term, highly flexible, hydrogen-ready gas power plants are used during longer phases of weak RE feed-in. They can be started up and shut down quickly and provide constantly available power in the form of electricity to meet demand. Accordingly, they help to maintain grid stability and play a key role in being able to reliably integrate a high share of renewable energies into the system. The power plants can initially be operated using natural gas and can be fully converted to run on climate-friendly hydrogen.

Download image
The Obrigheim site is composed of developed and undeveloped areas along the Neckar. The potential construction site for a CCGT plant borders the former nuclear power plant to the west (at the bottom of the picture) and is situated on previously unused land owned by EnBW (in the center of the picture).

The plans for Obrigheim

In southern Germany in particular, there is considerable demand for new, dispatchable – in other words, flexible – power plant capacity. A study commissioned by the transmission system operators revealed the need for an additional 6.5 gigawatts (GW) in TransnetBW’s grid area (Baden-Württemberg) alone. If this additional capacity were created, it may obviate the need to continue operating older coal power plants in the grid reserve in this area. Furthermore, due to legal regulations, all coal power plants in Germany must be shut down by no later than 2038.

The most important consideration in the region, however, is ensuring security of supply for electricity, which is why EnBW is contemplating the idea of a dispatchable, hydrogen-ready combined cycle gas turbine (CCGT) plant at the site:

Download image
  • The new, highly flexible plant, which would primarily be used for dispatchable power generation, would have a nominal electrical output of around 850 megawatts (MW), making it an ideal partner for generating power from renewable energies and important for maintaining security of supply in southern Germany.
  • Ever since 1974, the envisaged site has been designated in the development plan as an expansion area for the now decommissioned nuclear power plant in Obrigheim. This plan would simply need to be adapted to the current plans.
  • Continued use of the site would offer many advantages and would be particularly cost-effective given that the existing infrastructure and grid connection could be used.

As soon as enough hydrogen is available and the supply infrastructure in Germany has been converted to accommodate it, the power plant could produce carbon-neutral electricity. This would represent an important step toward generating climate-neutral electricity at the combined cycle gas turbine plant in Obrigheim.

New investments in dispatchable power plant capacity can only be made if the underlying legal conditions laid down as part of the planned Electricity Supply Security and Capacity Act allow the plants to be operated on a profitable basis and a corresponding funding concept is established. The Obrigheim project would then have to prevail over other planned national projects in a competitive tendering procedure.

Download image
This animation shows how the CCGT plant works and how heat is drawn off for district heating. No plans are envisaged to extract district or local heating in Obrigheim.

Technology

A combined cycle gas turbine (CCGT) plant marries the principles of a gas turbine and a steam power plant:

  • A gas-fired gas turbine produces electricity via a generator. The hot exhaust gases from the gas turbine are then channeled through a waste heat boiler, which uses the waste heat and generates superheated steam.
  • The resulting steam is used to power a steam turbine. This steam turbine also drives a generator to produce electricity.
  • By combining both processes, the energy from gas combustion is used twice, increasing the efficiency level to over 60 percent

The Obrigheim project is currently expected to have a nominal electrical output of around 850 megawatts (MW). Additional details about a new power plant, however, such as the layout of the installations, depend on further technical planning. Connecting the new power plant to the public gas grid would require the construction of a new gas pipeline route to the power plant site. Furthermore, the feasibility of a battery storage system next to the CCGT plant is currently being examined. There are no plans to extract district or local heating at the Obrigheim site.

Planning

Download image

Project phases

This is where we inform you about important events and milestones in relation to the preparation and potential construction of a combined cycle gas turbine (CCGT) plant on the Obrigheim site.

We wish to expressly point out that any implementation of the project would largely depend on the contract being awarded in the German government’s planned tendering process and that the corresponding legislative process has not yet been completed. We are holding an early public consultation before any potential invitation to tender so that the project can be realized in a timely manner. Below you will find the latest information on the timeline of the expected planning and approval process.

8 July 2026
Early public consultation
Expected to be September and December 2026
Competitive tendering process in line with the Electricity Supply Security and Capacity Act (StromVKG)
Expected to be October 2026
Scoping meetingFußnote0In complex planning processes, a scoping meeting is held by the authority overseeing the process (in this case Karlsruhe Regional Council). With the involvement of public agencies and specialist authorities, the meeting is used to formally determine the subject, scope and methodology of the regional impact and environmental impact studies as well as the content of the application documents that need to be drawn up. for the approval process in line with the Federal Immission Control Act (BImSchG)
Planned by October 2026
Resolution to be passed by Obrigheim Municipal Council to amend the development plan
Expected to be March 2027
Approval application submitted in line with BImSchG
less more

Questions and answers

Is Obrigheim gas power plant definitely being built?

No, the key prerequisite for a decision to build the project would be the awarding of the contract in the auction because that is the only way it would be economically viable. In addition, the project is still undergoing the approval process. Any decision to build the project will depend on the political conditions and the tendering processes within the context of the Electricity Supply Security and Capacity Act. A final investment decision would be linked to successful auction participation.

Why is a new gas power plant needed in Obrigheim?

Dispatchable power generation capacity is needed in Baden-Württemberg in order to reliably meet the demand for electricity at all times. Renewable energy sources cannot continuously meet this demand, and coal power plants should no longer be used for this purpose in the future due to their carbon emissions. Even though battery storage systems are dispatchable, they are only available for short periods of time (no more than a few hours) when needed. For this reason, gas power plants that can later be converted to use hydrogen as an energy source are set to close the existing gap.

In our view, the EnBW site in Obrigheim is well suited to the construction of such a gas power plant in Baden-Württemberg. The planned combined cycle gas turbine plant in Obrigheim is primarily designed to deliver a flexible electricity supply when there is insufficient wind and solar energy or grid stability needs to be maintained. Battery storage systems can only do this for a short period of time. Without the plant, coal power plants that produce significantly higher carbon emissions would have to provide the necessary cover in the longer term

Why is the new power plant not being built on the old site?

The task of dismantling the Obrigheim nuclear power plant is a complex project. It has reached an advanced stage, but is not yet complete. EnBW is currently going on the assumption that work to dismantle the power plant in line with nuclear power legislation can be completed in the early 2030s. Until then, the plant site is subject to monitoring under nuclear power legislation and therefore cannot be considered for reuse parallel to dismantling. However, it is not possible to wait that long to commence power plant projects aimed at meeting the demand for dispatchable power generation capacity, and the provisions of the Electricity Supply Security and Capacity Act are expected to require the commissioning of a new power plant in Obrigheim in the early 2030s.

What will happen to the old power plant site in the future?

No decision has yet been made in this regard, particularly since the site is not expected to be available until the early 2030s. Given the site’s good accessibility, its existing infrastructure and the stipulation in the state regional plans that it must be used for “energy-related” purposes, it stands to reason that energy in the broadest sense will feature in any future use.

EnBW is linking the planned gas power plant to the success of the energy transition. How can a power plant initially fired with a fossil fuel even be seen as part of the energy transition?

The term “energy transition” describes the path from electricity generation based on carbon emissions to carbon-free electricity generation. In this sense, a multistage decarbonization process involving one element of energy generation infrastructure also represents part of the energy transition. Even when operated using natural gas, a modern combined cycle gas turbine plant emits only half as much carbon per kilowatt-hour of electricity generated as a modern coal power plant, thus representing a first step toward decarbonizing electricity generation in a comparatively swift and cost-effective manner.

How is it possible to make a positive contribution to reducing greenhouse gases if the new gas power plant is being built while the existing coal power plants continue to operate as part of the grid reserve?

In terms of the energy transition and reducing gases that have an impact on the climate, it is not the installed power plant capacity that matters, but the amount of electricity generated in each power plant. The level of electricity demand in the market is driven by the consumers. For electricity generation and effective climate change mitigation, the question of which carbon emissions can be used to meet demand then becomes relevant. If building a new and highly efficient gas power plant (which can generate one kilowatt-hour of electricity with carbon emissions of around 370 g) results in a coal power plant previously operating in the intermediate range (with carbon emissions of over 800 g per kilowatt-hour of electricity generated) being transferred to the grid reserve, where, based on experience, it will only run for a small number of hours per year, this will really help to reduce carbon emissions, making it a key component of the energy transition. Investing in new dispatchable power plant capacity is also the basic requirement for gradually being able to completely decommission older coal power plants that have been transferred to the grid reserve on account of their system relevance.

What is the meaning of EnBW building a so-called H2-ready power plant if it will initially be operated solely as a gas power plant?

Natural gas (or methane) and hydrogen (H2) have very different properties, which means that it will always be necessary to convert a power plant before making the switch from natural gas to hydrogen. The key advantage of an H₂-ready power plant, however, is the fact that this conversion is technically possible in the first place, having already been taken into account in the basic design of the power plant components. As a result, the cost of subsequent conversions will only run to a small, single-digit percentage of the original investment cost. It is important that power plants like the one planned for Obrigheim can be converted with relatively little complexity as soon as hydrogen is available in sufficient quantities and at competitive prices. We are ultimately aiming to use 100 percent hydrogen. If natural gas is still needed for technical reasons following the switch to hydrogen – to start up the turbines, for example – this will only produce a small amount of carbon emissions due to the short start-up time of the turbines.

When is the switch to hydrogen planned?

That is difficult to predict at this point in time because it depends on many factors. The main questions here relate to when a sufficiently powerful connection to the planned upstream hydrogen core network will be possible. Then the hydrogen must be available on the market in sufficient quantities and must ultimately also be able to compete with other fuels in terms of cost, especially natural gas. The last point could also be achieved through regulatory measures, for example, such as two separate hydrogen tendering processes, as set out in the cabinet resolution relating to the Electricity Supply Security and Capacity Act. On the other hand, a binding switch to hydrogen or climate-neutral operation of the plants is also required from 2045 as part of the regulatory framework. Based on current estimates, EnBW expects a changeover date sometime in the second half of the 2030s.

Is EnBW then talking about green hydrogen or rather blue hydrogen, which is ultimately obtained from natural gas by a process known as steam reforming?

EnBW’s clear aim is to use green hydrogen. During the ramp-up phase in particular, however, it may well be that green hydrogen alone would not be available in sufficient quantities or would still be too expensive due to the existing cost structure. Among other things, this would delay the switch to hydrogen. Blue hydrogen, which is produced in a process known as steam methane reforming, is much more cost-effective. The CO₂ that is produced in this process is captured before being permanently stored. Blue hydrogen is therefore a sensible bridging option, not least because the actual product is essentially identical to green hydrogen, which means that it can gradually be substituted by green hydrogen at a later date without having to make further changes to the power plant technology or supply pipelines. We therefore consider it legitimate to look for cheaper ways to achieve the desired decarbonization of dispatchable electricity generation, even if this may involve intermediate steps – via so-called blue hydrogen, for example. For this reason, EnBW is advocating approval of the use of blue hydrogen within the regulatory framework, but that in itself is not the same as EnBW solely wanting to use blue hydrogen in the long term.

In which phase of the approval process and public consultation is the project right now?

Various approval procedures need to be completed before the project can be approved, including the amendment of the development plan, the approval procedure under the Federal Immission Control Act and the planning approval process. We are still at the start of all these approval procedures. The project is currently in the early public consultation phase as part of the development plan procedure pursuant to Section 3 (1) of the Building Code and the early stages of the public consultation process pursuant to Section 2 of the Environmental Administration Act. The municipality of Obrigheim and EnBW are holding a public event on 8 July 2026 to provide people with information on the general objectives, purposes and expected impact of the planned combined cycle gas turbine plant. In addition, the draft development plan will be made available online for a certain period of time for people to view. During this period, members of the public can submit their opinions. A further public review phase is planned for a later date.

News, dates & contact
Dates

No events are currently planned.

Contact

Do you have any questions? We will be happy to assist you!

Project

Email:

Corporate Communications

Email:

Download Accept Decline Download now

Downloads

Obrigheim gas power plant: early public consultation process