Heilbronn combined heat and power plant is located in an industrial and commercial park by the Neckar on the outskirts of the city and is one of EnBW’s largest hard coal power plants. Of the original seven hard coal-fired blocks on the site, three are still in operation, producing electricity and district heating in combined heat and power mode. While the two older Blocks 5 and 6 are part of the grid reserve to guarantee grid stability, Block 7 was extensively modernized back in 2009. For balancing purposes, a battery energy storage system with a capacity of five megawatt-hours was commissioned at the power plant in 2017. EnBW has set itself the goal of phasing out coal-fired power generation before the legally mandated phase-out, provided regulatory and economic conditions allow for it. As part of this strategy, the site will be converted to run on hydrogen in the future (known as a fuel switch): A new combined cycle gas turbine plant will initially be operated using natural gas to generate electricity and district heating and can be converted to run on hydrogen as a fuel at a later date.
Fuel Switch
EnBW is consistently continuing the decarbonization of its generation portfolio with the expansion of renewable energies. Due to legal requirements, all coal power plants in Germany must also be shut down by no later than 2038, including the plant in Heilbronn. The most important consideration in the region, however, is guaranteeing security of supply for electricity and district heating, which is why EnBW is building a controllable, hydrogen-ready combined cycle gas turbine (CCGT) plant at the site:
- The new, gas-fired plant has an electrical output of 675 megawatts (MW) and a thermal output of around 190 MW.
- In addition, a hot water boiler system with a thermal output of around 160 MW and a heat storage facility with a capacity of 600 megawatt-hours will supply district heating in Heilbronn.
- This fuel switch to natural gas can reduce greenhouse gas emissions by more than half compared to coal-fired power generation.
As soon as hydrogen is available in sufficient quantities and the supply infrastructure has been converted accordingly, the power plant can operate on hydrogen, which would allow for an even greater reduction in CO₂ emissions from electricity and district heating generation compared to coal-fired power generation. That’s because, like the plant itself, the natural gas pipeline that supplies the CCGT is hydrogen-ready, which means that the switch to hydrogen can be made at a later date with no major hurdles. Find out more about the fuel switch here.
A combined cycle gas turbine (CCGT) plant marries the principles of a gas turbine and a steam power plant:
- A gas-fired turbine produces electricity via a generator. The very hot exhaust gases from the gas turbine are then channeled through a waste heat boiler
- The resulting steam is used to power another turbine. This steam turbine also drives a generator to produce electricity
- By combining both principles, the energy from gas combustion is used twice, increasing the efficiency level to as high as 60 percent.
The district heating produced while generating electricity will be fed into the district heating grid in Heilbronn, which is currently being extensively upgraded and converted from a steam network into a heating water network. The new heating water network is designed to reduce system losses and enable more efficient use of the fuels used. Find out more about the modernization measures here.
Approach
Project phases
This is where we inform you about important events and milestones relating to the planning and construction of a combined cycle gas turbine (CCGT) plant on the Heilbronn site. You will find the latest information here on the timetable for the planning and approval process as well as the progress of the construction work.
|
Provisionally Q23/Q4 2027
|
Commercial commissioning
|
|
2026/2027
|
Start-up phase
|
|
2025/2026
|
Main construction activities
|
|
March 2024
|
Start of plant construction work
|
|
December 2024
|
Start of delivery of major components
|
|
July 2024
|
Receipt of the 1st partial permit
|
|
June 2024
|
Start of shell construction work
|
|
23 February 2024
|
Official groundbreaking ceremony
|
|
22 January 2024
|
Stuttgart Regional Council meeting to discuss the project
|
|
24 November 2023
|
Approval for advance construction work to begin
|
|
June 2023
|
Approval application submitted
|
|
2022/2023
|
Early public consultation process, presentation to the Municipal Council, expert reports produced
|
Project diary
August 2026: A transient village
Around 800 people currently work daily on the Heilbronn 8 construction site. The solid organization, clear processes and good working relationship among the experienced team have turned the site into a kind of “transient village”. In order to ensure that this works well throughout the project, health and safety specialists are present on the construction site, including a paramedic, who is always on hand to react quickly when needed. The fact that this has rarely been necessary to date is revealed by an important interim statistic: more than 200 accident-free days on the construction site. Orderliness and cleanliness are also firmly integrated into the plans. A dedicated housekeeping team takes care of waste disposal on a daily basis and makes sure that all areas remain clean and tidy, enabling employees to concentrate on their actual tasks. The HSE (health, safety and environment) team ensures that safety standards are met. The employees can be approached on the construction site to provide information and assistance with regard to organizational or safety-related matters. The gate also controls access to the site around the clock, increasing security and providing an overview of who is on the construction site. This is particularly useful because people no longer only work from Monday to Friday – around 570 workers now also report for duty on Saturdays. Together, they are working to complete one of the region’s main large-scale energy infrastructure projects, shaped by technology, teamwork, clear structures and good cooperation.
July 2026: New gas pipeline commissioned
The new gas pipeline has been successfully brought online, connecting Heilbronn power plant with the existing gas grid in the area of the Böllinger Höfe industrial park and crossing the Neckar via a culvert that runs beneath the river. In the course of commissioning, the pipeline was filled with natural gas for the first time and subjected to extensive functional tests. A planned and safety-related aspect of the process involves the controlled flaring of gas. This serves to eliminate the existing air in the pipeline in a controlled manner to enable safe operation of the gas pipeline. That is why a flare could be seen at certain times on the power plant site. Due to the ongoing drought conditions, the surrounding trees were watered as a precautionary measure during this work to protect them from the heat generated. The new infrastructure forms the basis for the subsequent work to commission the fuel switch plant.
May 2026: The new heat storage facility is filled
The new heat storage facility, which can be seen from miles around, was filled with water in May. With a diameter of around 20 meters and a height of 58 meters, it can hold about 18,000 cubic meters of water. The inside is designed in such a way that enables the creation of different temperature zones: In the main storage zone, the water can later be heated to up to 120 degrees Celsius, while in the upper, so-called load section, the maximum temperature is 99 degrees Celsius. This differentiated temperature control means that the storage facility can be operated particularly efficiently. Water from the existing district heating grid was used to fill it, making it possible to check whether the storage tank was absolutely leakproof under real conditions. The next step involves insulating the tank. An insulation layer around 50 centimeters thick will cover the storage tank in the future, allowing the generated heat to be stored with as little loss as possible. The water will then remain permanently in the tank and will not be drained again during its entire service life. It will be continuously monitored to see how the structure behaves under the huge load of the water. Both the stability of the foundations and the entire structure will be kept under observation with the aid of precise measurements.
April 2026: Installation of the third chimney element
Another important milestone was reached in April as part of the fuel switch project at the Heilbronn site when the third of a total of four chimney sections of the new hot water boiler system was successfully installed. The chimney is a key part of the plant and is increasingly shaping the overall look of the construction site.
Inside there are four separate flues, each serving to channel the exhaust gas of the individual boilers. The installation of the third element marks the end of a significant stage of the construction project, which means that completion is now a major step closer. The work went according to plan and in compliance with high safety and quality requirements. Once all four chimney sections have been completed, the next steps will involve installing the final equipment and integrating everything into the entire plant.
February 2026: HiDE 3 boiler house expansion
The existing HiDE 3 boiler house is currently being comprehensively expanded as part of the fuel switch project, with the building receiving two additional hot water boilers to perfectly complement the system’s two existing steam boilers. Their future role will be to secure the district heating grid supply if the new combined cycle gas turbine plant is temporarily unable to supply hot water – due to insufficient utilization, for example. One particular challenge involves the existing steam boilers remaining in operation throughout the entire construction phase. At the same time, the flue gas ducts are being installed on the roof. The new chimney to vent the exhaust gas has already reached half its height and is set to be completed after Easter when the final components are added. The work is thus continuing apace, but requires a great deal of coordination, not least because around fifteen different trades are working on the construction site at the same time, including scaffolders, facade installers, roofers, fitters and welders.
January 2026: visible progress
After the Christmas break, life has returned to the HLB8 construction site. Several buildings have now reached the enclosed stage – which means that the outer shells have been completed, providing the basis for the inside work. Here, too, there is visible progress, with pipes, technical systems and other components gradually being installed and the individual spaces increasingly taking shape. Numerous cranes can still be seen in operation on the site, conveying building materials to the right places – a daily logistical challenge that the team masters with a great deal of coordination. Everything is going according to plan: The construction site is well organized and work is swiftly progressing. All in all, a successful start to the new year!
December 2025: Installation of the overhead cranes in the turbine hall
In December, two powerful overhead cranes were installed in the turbine hall of the new CCGT plant. These cranes will perform key tasks during future maintenance and inspection work on turbines and generators. Each of the two cranes has a lifting capacity of up to 70 metric tons. Tandem lifting makes it possible to move up to 140 metric tons. The crane runway is installed at a height of around 23 meters and extends over a length of some 86 meters. Components were delivered individually before being assembled on-site. A 650-ton mobile crane was used to lift the heavy double-girder crane runways. The work had to be carefully coordinated at all times so as not to damage the existing steel structure. This project shows how good planning and professional execution can combine well, with every step precisely coordinated – from the preparation and organization to the assembly. The result is a technically sophisticated installation that meets the highest safety and quality standards.
October 2025: Installation of the air intake system for the gas turbine
The air intake system for the gas turbine was installed in October 2025. The intake air passes through several filter stages, resulting in highly efficient separation of the particles contained in the air: from coarse dust and sand to particulate matter such as pollen and microscopic soot particles. This ensures that only purified air ends up in the combustion process that drives the turbine. Around 2.5 million cubic meters of air per hour flow through the filter house. By way of comparison, an adult person inhales between 7.2 and 10.5 cubic meters of air in the same period. The installation represents another important step in the technical upgrading of the plant.
September 2025: Building the district heating storage facility
Work to build the district heating storage facility was completed at the end of September 2025. The storage facility makes it possible to store excess heat on an interim basis and release it as and when needed. Construction work began in December 2024, with the individual sheets of metal being inserted from the bottom up and bolted together so that the storage facility gradually grew upward. Work on the insulation then got under way. Many industrial companies and households are connected to Heilbronn’s district heating network and supplied by it. The district heating storage facility is part of the expansion of this district heating system and will serve to store thermal energy in the future.
Find out more in the video here.
June 2025: Sliding in gas turbine and rotor
A significant milestone has been reached on the construction site following the successful installation of the new gas turbine and the generator rotor, the key components of the planned combined cycle gas turbine plant. The components from Japan and France have now been installed in their designated position with high precision and detailed coordination. The team had to slide the gas turbine over a distance of 50 meters during installation. That is no easy task when it weighs 380 metric tons and is being slid into position at a speed of about two meters per hour. It has to be exact down to the last millimeter!
Find out more in the video here.
April 2025: Slipforming of the chimney
The slipforming of the chimney is now complete. This is a construction method where concrete is poured continuously into a moving form until the chimney reaches a certain height. A special sliding structure, known as a slip form, makes it possible to pour the concrete in one go while the formwork moves upward and the concrete hardens. Once the desired height has been reached, the slip form is removed and work can continue on the chimney. This is how the chimney continuously grew to a final height of 144 meters over a period of five weeks.
Find out more in the video here.
March 2025: Boiler pressure modules assembled
Work has begun on lifting the boiler pressure modules into position and slipforming the chimney. The 15 boiler modules, each weighing up to 230 metric tons, are gradually being lifted into position with the aid of one large and one small crane. The large crane has a lifting capacity of up to 1,350 metric tons. In the boiler, the heat from the hot exhaust gas is transferred from the gas turbine to generate steam, which in turn drives the steam turbine.
February 2025: Erection of steelwork ramped up
The foundations and excavation work are progressing rapidly. The turbine hall and the boiler house – clearly recognizable by the blue steelwork – are gradually taking shape. In the next step, the boiler pressure modules can be installed in the boiler house. At the same time, work will begin on building the 60-meter-tall heat storage facility. Preparations are also being made to slipform the CCGT plant’s 144-meter-tall chimney. (Image source: Züblin drone shot)
January 2025: Gas turbine delivered
Following completion of the foundation work, it has now been possible to start building the plant. The blue of the first steel structures can already be seen on the construction site. The gas turbine and generator were also delivered in January – marking an important step for the project. (Photographer: Markus Völter)
November 2024: Work is progressing
Considerable progress was made on the construction site in November 2024. In addition to the foundations, floor slabs and the first of the buildings, the excavation work is also progressing nicely. On the site that was still a field at the start of the year, the outlines of the buildings are now visible and the power plant is slowly taking shape. A total of 1,600 bored piles have already been made and work is now continuing on the construction of the above-ground structures. Building work on the actual plant itself will begin in the new year.
September 2024: New shell construction work
Following the completion of the pile foundations, shell construction work started in July, which included making the base plates and concrete buildings. The foundations have been reinforced so that they can handle the heavy loads of the main components encased in concrete later on. The reinforcements for the power train can be seen in the photo.
July 2024: Receipt of the 1st partial permit in accordance with the Federal Immission Control Act (BImSchG)
We have received the 1st partial permit in accordance with the BImSchG for our planned power plant! Receipt of this permit marks an important milestone for our project and means that we can now get started on all construction work. As part of the 2nd partial permit, we will next apply for approval to operate the power plant. This is another step not only towards constructing our power plant but also towards being able to operate it fully licensed. We plan to submit the application by the end of 2024. The public were involved in this process. Prior to receiving notification of the 1st partial permit, we had already received a notice of early commencement from the responsible licensing authorities. This permitted us to start certain construction work – at our own risk – even before receipt of the actual permit. Construction work has been underway in Heilbronn on this basis since November 2023. The approval process took a total of 13 months.
April 2024: Work starts on the bored pile foundations
The foundation phase of the construction project is progressing with the construction of around 1,600 bored piles. The bored pile foundations have been designed in such a way that the future loads from the new CCGT power plant will be transferred to the load-bearing Lower Keuper bedrock at a depth of around 10 meters. They bypass layers with less load-bearing capacity in the process. The start of this construction work marks an important milestone for the project team.
March 2024: Renovation work on the cooling tower completed
Work began on renovating the natural draft wet cooling tower in July 2023, during which both the cooling installations and the drift eliminators (pictured) were renewed and the water distribution system was renovated. This work was completed in March. The cooling tower will continue to be used by the new plant.
February 2024: Groundbreaking ceremony and official opening of the building site
Following the start of construction work at the Heilbronn power plant site, EnBW’s third so-called “fuel switch” project is now also underway. The State Secretary from the Ministry of the Environment of Baden-Württemberg Andre Baumann, Chief Mayor Harry Mergel, Plant Manager of the Audi site in Neckarsulm Fred Schulze, EnBW Board Member Dirk Güsewell and Head of Generation Portfolio Development Michael Class held the traditional groundbreaking ceremony on 23 February 2024.
June 2023: Contracts signed for the development plan
The first milestone of the fuel switch project in Heilbronn was reached on 28 June 2023 when the urban development contracts for the development plan were signed, paving the way for the construction of the power plant by laying the necessary legal and planning foundations with the city.
Photo (back row, from left: Christoph Rundel (Planning Manager at the Planning and Building Law Department), First Mayor Martin Diepgen, City Councilor for Construction Andreas Ringle, Tilmann von Frantzius (Planning and Building Law Department), Diana van den Bergh (EnBW Project Manager), Jens Rathert (EnBW Project Manager); front row: Chief Mayor Harry Mergel, EnBW CEO Dr. Georg Stamatelopoulos).
Frequently asked questions
The groundbreaking ceremony for the construction project was held on 23 February 2024. Construction work began in November 2023 because a permit had been obtained to start early. The main construction activities are expected to be completed by 2027, followed by the start-up phase and commercial commissioning.
Unfortunately, it is difficult to fully avoid construction work being noticeable in the area. However, EnBW is making every effort to minimize the impact. Most of the work is carried out during the day, with heavy haulage moved to nighttime whenever possible.
All measures will be carried out as per the approval process and in close consultation with Stuttgart Regional Council and the city of Heilbronn. EnBW also continues to engage in dialogue with residents to address their concerns and questions.
The existing power plants will remain in operation until all new power plant and district heating facilities have been fully commissioned, ensuring that the power supplied by the power plant and the district heating supply in the city of Heilbronn and the surrounding region is reliably maintained at all times.
If you have any questions, suggestions or criticism, please contact heilbronn@enbw.com at any time.
EnBW provides regular information on the progress of the project and current milestones. This is done via the project page, which can be found at www.enbw.com/heilbronn, and by distributing leaflets. Media outlets also report on the progress on the construction site at regular intervals.
As part of the approval process, noise reports and similar reports are produced to assess the impact of the new building on the surrounding area.
Once the new combined cycle gas turbine (CCGT) plant has been commissioned, blocks HKW 1 and HKW 2 are scheduled to shut down. Only a few large components – such as the gas turbine plants, the HKW 1 cooling tower and the water treatment plant –are expected to remain in operation. Since the decommissioned plants previously made a significant contribution to the noise emissions at the site, the overall noise situation may improve.
The CCGT will be fitted with the latest generation of silencers and sound traps in order to comply with the legal limits laid down by noise control regulations (TA Lärm). In addition, there will no longer be any disposal of residues or delivery of additives associated with the coal blocks’ flue gas cleaning system, which in turn could reduce the volume of traffic.
As part of the approval process, reports such as an air pollutant forecast are produced to assess the impact of the new combined cycle gas turbine (CCGT) plant on the surrounding area.
The planned switch from coal to natural gas has the potential to reduce emissions of CO₂ and other climate-impacting substances. For Heilbronn, current plans call for a reduction in CO₂ emissions of approximately 50% compared to the current coal-fired power plant. This amounts to over one million metric tons of CO₂ per year. Forecasts also indicate a reduction in other air pollutants: Emissions of nitrogen oxides (NOₓ) could drop by about 80% compared to current levels, and those of sulfur oxides (SOₓ) by more than 90%. In addition, dust pollution is expected to decrease by 44 percent, and heavy metal emissions – which occur during coal-fired power generation – will cease after the transition.
As part of the approval process, reports are produced, including a survey on the impact on water pollution control, in order to assess the impact of the new building on the surrounding area.
According to current plans, the commissioning of the combined cycle gas turbine (CCGT) plant and the subsequent decommissioning of the old plants will result in significantly less heat being released into the Neckar, which borders the power plant site, compared with today. This can contribute to an improvement in water pollution control compared to the current situation.
There are two parts to the approval process for the combined cycle gas turbine (CCGT) plant pursuant to the Federal Immission Control Act (BImSchG):
- The first part of the application was submitted in June 2023. EnBW was granted the partial permit for this in July 2024.
- The second part of the application was submitted in June 2025. The plant is expected to be commissioned in 2027.
Stuttgart Regional Council is the approval authority. The city of Heilbronn already made adjustments to the development plan for the site back in 2022.
EnBW currently estimates that a mid-three-digit million euro amount will be invested in the construction project.
Two new main structures are being built on the existing power plant site:
- The combined cycle gas turbine (CCGT) plant and its auxiliary facilities are being built in the area situated to the east of the cooling tower.
- A district heating storage facility is also being built, which is also located in the area situated to the east of the cooling tower.
Plans for the future use of the freed up areas are currently still open and will be decided at a later date.
The decision in favor of a combined cycle gas turbine (CCGT) plant is based on its high degree of efficiency:
- For a reliable energy supply, it is essential to use the fuel as efficiently as possible in order to generate as much electricity and heat as possible from a given amount.
- By combining electricity and heat generation in the combined heat and power process, a CCGT plant can achieve a fuel utilization rate with an efficiency level of over 60% based on the current state of the art.
In the field of heat generation in particular, renewable energies are currently not in a position to fully replace fossil fuel within a matter of years and in all applications.
Natural gas is therefore considered a temporary solution, not least because it has the potential to reduce greenhouse gas emissions compared to coal. It is important to remember that natural gas is only intended to be used for a transitional period.
The gas turbines are flexible and can later be converted to burn other gases such as green hydrogen. Green hydrogen is produced by means of electrolysis using electricity from renewable energy sources.
As soon as the combined cycle gas turbine (CCGT) plant is commissioned, it will be possible to add up to 20% hydrogen to the natural gas according to current plans, which can further reduce greenhouse gas emissions. The switch to natural gas thus represents a transitional step culminating in a future energy supply with hydrogen.
The new combined cycle gas turbine (CCGT) plant supports the security of supply and can complement the fluctuating energy production from renewable energy sources. In the initial phase, the CCGT plant will provide electricity and district heating with lower CO₂ emissions than coal-fired power generation.
In the long term, the plant could contribute to a further reduction in CO₂ emissions if it operates using hydrogen as fuel. Based on current technology, a combined-cycle gas turbine plant produces lower emissions of certain air pollutants than older fossil-fuel-fired power plants.
Not directly and not all the time. Converting an urban area to run on regional renewables is a complex challenge. This is mainly due to the fact that renewable energy sources such as wind power and photovoltaics require a lot of space because their energy density is comparatively low.
What’s more, these energy sources are not dispatchable – they generate electricity when the wind or sun is available, and not necessarily when energy demand is at its highest. In order to compensate for these fluctuations, flexibly dispatchable power plants are needed to meet demand.
A combined cycle gas turbine (CCGT) plant consists of a gas turbine, a steam turbine and heat exchangers for the production of hot water. It utilizes the energy generated during the combustion of natural gas in a particularly efficient manner by using the produced heat three times:
1. Electricity generated by the gas turbine: The hot combustion gases produced during the combustion of natural gas firstly drive a gas turbine. This is connected to a generator that converts the turbine’s mechanical energy into electrical energy.
2. Additional electricity generated by the steam turbine: The exhaust gases from the gas turbine are still very hot. This heat is used in a waste heat boiler to evaporate water. The steam drives a steam turbine, which also generates electricity.
3. Further use made of the residual heat: Part of the steam that has already been used to generate electricity is withdrawn from the steam turbine and used to generate district heating. This process is much more efficient compared to direct heat generation in boiler systems.
This combined heat and power generation enables the CCGT plant to achieve a fuel utilization rate of over 70% based on current state-of-the-art technology. With this approach, CO₂ emissions can be reduced by about 50% compared to those produced by a coal power plant according to current plans. Switching from coal to natural gas is therefore viewed as a transitional step that can contribute to a reduction in greenhouse gas emissions.
The combined heat and power generated by the combined cycle gas turbine (CCGT) plant allows the particularly efficient use of natural gas as a fuel and offers the possibility of fully switching to hydrogen in the future.
In the initial phase, a blend of natural gas and up to 20% hydrogen would be used, provided that it is available in sufficient quantities. Starting around the late 2030s, adjustments would then make it possible to operate on 100% hydrogen.
The combined cycle gas turbine (CCGT) plant could offer the following advantages over the hard coal blocks that have been used until now in Heilbronn:
- The gas-fired plant can be controlled more flexibly than a coal-fired power plant and can therefore better compensate for fluctuations in wind and solar power.
- Combined heat and power (CHP) in the gas-and-steam (GuD) plant contributes to efficient fuel utilization. In the future, conversion for the use of hydrogen is possible, provided the technical and economic requirements are met.
- Natural gas produces lower direct CO₂ emissions compared to hard coal. According to current plans, emissions per kilowatt-hour of electricity generated could fall by more than 50% starting in 2027 – depending on the operating mode.
- According to forecasts, a reduction in air pollutants is expected: nitrogen oxide emissions (NOₓ) and sulfur oxide emissions (SOₓ) will decrease significantly, and particulate matter pollution will drop by about 44 percent; heavy metal emissions from coal combustion will be eliminated.
- With the decommissioning of the coal-fired units, the existing coal storage facility will be eliminated, thereby eliminating the dust and noise emissions previously associated with it.
- Traffic volume may decrease, as coal deliveries will no longer be necessary and additional transport for flue gas cleaning will largely be eliminated.
- The plant’s noise level is to be limited through modern noise reduction technology. In addition, coal-fired boilers, auxiliary steam generators, and flue gas cleaning systems will be taken out of service.