EnBW is planning a state-of-the-art sewage sludge combined heat and power plant on its existing power plant site in Walheim. Around 180,000 metric tons of local sewage sludge are set to be disposed of or recycled in a sustainable manner here. The plant meets the requirements for recovering phosphorus, an important raw material for agriculture, from the sewage sludge. Extracting environmentally friendly district heating will provide a sustainable supply for up to 300 households.
Sewage sludge utilisation
Project introduction
As coal is phased out, renewable energy sources are gradually replacing it to supply power. This transformation carries with it the challenge of developing sustainable solutions for other areas of life. One example involves how to deal with sewage sludge. Every year, between seven and eight million metric tons of sewage sludge are produced in Germany, a by-product of wastewater treatment at sewage treatment plants. Until now, most of this has been incinerated in coal power plants. However, since these will soon no longer be available, there is a need to find new eco-friendly ways of disposing of sewage sludge and recovering valuable resources such as phosphorus from it.
Phosphorus is indispensable for all biological organisms because it plays a key role in forming the structural framework of DNA and supplying cells with energy. In agriculture, the vital plant nutrient is added to the soil in the form of fertilizers to promote growth. Since the direct use of sewage sludge as a fertilizer has been severely restricted due to concerns about pollutant loads, the recycling of phosphorus from sewage sludge is all the more important. At present, Germany has to source 100 percent of its phosphorus from abroad. Consistent recycling of phosphorus could replace up to 40 percent of these imports.
From 2029/2030, it will be required by law to recover up to 80 percent of phosphorus from sewage sludge – for cities and larger municipalities, this will apply from 2029, for smaller local authorities with their own sewage treatment plants from 2032. That being the case, the first plants to recycle sewage sludge sustainably have already been built in Germany over the course of recent years. These plants are virtually emission-free and produce ash containing phosphorus. This residual product is then used as a raw material in the production of fertilizers. Besides reducing the country’s dependence on imports, recycling this valuable material is also very sustainable.
Such a sewage sludge combined heat and power plant is being built in Walheim. On the site of the now decommissioned coal power plant, parts of the old power plant are being dismantled to make room for the new plant. In addition to serving the purpose of incinerating sewage sludge, the project is embracing other sustainable concepts, such as the promotion of e-mobility and the use of climate-friendly heating. Accordingly, Walheim sewage sludge combined heat and power plant not only has an essential role to play in the energy transition, but will also support local interests and be important far beyond the region itself.
Technology
The previous power plant in Walheim was built between 1962 and 1967 and consists of two coal-fired blocks. In the winter of 1981/1982, a gas turbine powered by light fuel oil was added, which is quickly ready for operation and feeds electricity into the grid during times of peak demand. Although the two coal-fired blocks were registered for decommissioning back in 2014, they were classified as having system relevance by the Federal Network Agency until March 2025. The coal-fired blocks were finally decommissioned in March 2025, while the gas turbine remains in operation.
The new sewage sludge combined heat and power plant is now being built on part of the former coal dump. The planned plant will consist of a closed storage bunker, a fluidized bed furnace for incinerating the sewage sludge and a modern flue gas cleaning system. Flue gas is produced during the incineration of sewage sludge, which is channeled into a waste heat boiler to generate steam. This drives a steam turbine to produce electricity. The cooled flue gas is then cleaned in a multi-stage flue gas cleaning system, separating the ash, from which valuable phosphorus can be recovered. This recycling process is carried out elsewhere by specialist companies in a central location.
The vapors produced during the drying of the sewage sludge are cleaned and condensed in the vapor processing area, where up to four megawatts can be extracted for district heating, enough to supply around 300 households with energy. State-of-the-art technology prevents any potential odor pollution, with the combustion air being sucked out via a reception and storage bunker during operation, creating negative pressure. Together with an airlock system, this prevents odors from escaping outside. During downtime or maintenance, the exhaust air is guided through a filter system. The very strict conditions stipulated in the first partial permit guarantee clean operation.
Sewage sludge is already being incinerated and added to the fuel in coal power plants. The incineration plant specially planned for Walheim clearly surpasses this method: it is low-emission and significantly reduces carbon emissions. In addition, the ash produced during incineration contains valuable phosphorus that can be recycled – a measure prescribed by legislation from 2029/2030. In modern plants, the ash containing phosphorus can be better processed and then further treated by specialized companies at another location. This is not possible with co-incineration at coal power plants.
Specifications
The plant can incinerate around 180,000 metric tons of dewatered sewage sludge each year, based on an annual operating time of 8,000 hours. It has a thermal output of up to 4 MW for local heating and an electrical output of about 1.5 MW.
| 
    	                		                	                                        	                                                                                             Plant capacity 
    	                		                	                                        	                                                                                     | 
    	                		                	                                        	                                                                                             around 180,000 t/a of dewatered sewage sludge (equivalent to 50,000 t/a of dry matter) and around 5,000 t/a of dried sewage sludge 
    	                		                	                                        	                                                                                     | 
    	                		                	                                        	                                                                                
| 
    	                		                	                                        	                                                                                             Dry matter content of delivered sewage sludge 
    	                		                	                                        	                                                                                     | 
    	                		                	                                        	                                                                                             20-30% dry matter 
    	                		                	                                        	                                                                                     | 
    	                		                	                                        	                                                                                
| 
    	                		                	                                        	                                                                                             Throughput 
    	                		                	                                        	                                                                                     | 
    	                		                	                                        	                                                                                             approx. 20 metric tons of dewatered sewage sludge per hour 
    	                		                	                                        	                                                                                     | 
    	                		                	                                        	                                                                                
| 
    	                		                	                                        	                                                                                             Operating time 
    	                		                	                                        	                                                                                     | 
    	                		                	                                        	                                                                                             over 8,000 hours per year 
    	                		                	                                        	                                                                                     | 
    	                		                	                                        	                                                                                
| 
    	                		                	                                        	                                                                                             Electrical output 
    	                		                	                                        	                                                                                     | 
    	                		                	                                        	                                                                                             approx. 1.5 megawatts electrical 
    	                		                	                                        	                                                                                     | 
    	                		                	                                        	                                                                                
| 
    	                		                	                                        	                                                                                             Local heating 
    	                		                	                                        	                                                                                     | 
    	                		                	                                        	                                                                                             up to 4 megawatts thermal 
    	                		                	                                        	                                                                                     | 
    	                		                	                                        	                                                                                
Approach
Project phases
This is where we inform you about important events and milestones relating to the planning and construction of a sewage sludge combined heat and power plant on the Walheim site. You will find the latest information here on the timetable for the planning and permit process as well as the progress of the construction work.
| 
    	                		                	                                        	                                                                                             Q1 2028 
    	                		                	                                        	                                                                                     | 
    	                		                	                                        	                                                                                             Commercial commissioning 
    	                		                	                                        	                                                                                     | 
    	                		                	                                        	                                                                                
| 
    	                		                	                                        	                                                                                             Q3 2027 
    	                		                	                                        	                                                                                     | 
    	                		                	                                        	                                                                                             Start-up phase 
    	                		                	                                        	                                                                                     | 
    	                		                	                                        	                                                                                
| 
    	                		                	                                        	                                                                                             2026 
    	                		                	                                        	                                                                                     | 
    	                		                	                                        	                                                                                             Installation of plant technology 
    	                		                	                                        	                                                                                     | 
    	                		                	                                        	                                                                                
| 
    	                		                	                                        	                                                                                             June 2025 
    	                		                	                                        	                                                                                     | 
    	                		                	                                        	                                                                                             Receipt of the 1st partial permit 
    	                		                	                                        	                                                                                     | 
    	                		                	                                        	                                                                                
| 
    	                		                	                                        	                                                                                             Q2 2025 
    	                		                	                                        	                                                                                     | 
    	                		                	                                        	                                                                                             Start of shell construction work 
    	                		                	                                        	                                                                                     | 
    	                		                	                                        	                                                                                
| 
    	                		                	                                        	                                                                                             February 2025 
    	                		                	                                        	                                                                                     | 
    	                		                	                                        	                                                                                             Bored piles for the foundations 
    	                		                	                                        	                                                                                     | 
    	                		                	                                        	                                                                                
| 
    	                		                	                                        	                                                                                             October 2024 
    	                		                	                                        	                                                                                     | 
    	                		                	                                        	                                                                                             Approval for advance construction work to begin 
    	                		                	                                        	                                                                                     | 
    	                		                	                                        	                                                                                
| 
    	                		                	                                        	                                                                                             November 2023 
    	                		                	                                        	                                                                                     | 
    	                		                	                                        	                                                                                             Completion of documentation for the approval application 
    	                		                	                                        	                                                                                     | 
    	                		                	                                        	                                                                                
| 
    	                		                	                                        	                                                                                             March 2023 
    	                		                	                                        	                                                                                     | 
    	                		                	                                        	                                                                                             Approval application checked by the authorities to ensure it is complete 
    	                		                	                                        	                                                                                     | 
    	                		                	                                        	                                                                                
| 
    	                		                	                                        	                                                                                             February 2023 
    	                		                	                                        	                                                                                     | 
    	                		                	                                        	                                                                                             Approval application submitted 
    	                		                	                                        	                                                                                     | 
    	                		                	                                        	                                                                                
| 
    	                		                	                                        	                                                                                             26 October 2022 
    	                		                	                                        	                                                                                     | 
    	                		                	                                        	                                                                                             Scoping meeting* held by Stuttgart Regional Council 
    	                		                	                                        	                                                                                     | 
    	                		                	                                        	                                                                                
| 
    	                		                	                                        	                                                                                             Start of 2022 
    	                		                	                                        	                                                                                     | 
    	                		                	                                        	                                                                                             Dialogue with the municipality 
    	                		                	                                        	                                                                                     | 
    	                		                	                                        	                                                                                
| 
    	                		                	                                        	                                                                                             2020/2021 
    	                		                	                                        	                                                                                     | 
    	                		                	                                        	                                                                                             Early public consultation process, presentation to the Municipal Council, expert reports produced 
    	                		                	                                        	                                                                                     | 
    	                		                	                                        	                                                                                
* In complex planning processes, a scoping meeting is held by the authority overseeing the process (in this case Stuttgart Regional Council). With the involvement of public agencies and specialist authorities, the meeting is used to formally determine the subject, scope and methodology of the regional impact and environmental impact studies as well as the content of the application documents that need to be drawn up.
Construction Diary
Construction diary
September 2025
Work has begun on the construction of the reinforcement and formwork for the sewage sludge bunker building at the construction site. The reinforcement will later ensure the necessary stability and load-bearing capacity. The formwork serves as a mold for the concrete, preventing it from leaking during pouring.
August 2025
The floor slabs, whose reinforcement has already been completed, have now been concreted. The concreting is being carried out in several stages.
July 2025
The reinforcement for the floor slabs was installed. The reinforcement bars are laid and fixed in place with spacers.
June 2025
The heads of the bored piles were sprayed off, freeing the reinforcement from the concrete so that the connection to the floor slab can be made. The future floor slab will be supported by these piles.
April 2025
In the area of the planned new building, a total of eight test pits were dug on the site of the coal storage facility so that soil samples could be taken. To this end, the horizontal layer of coal, varying in thickness, was removed. Then the test pits were dug (see photo). Horizontal samples were taken from the material that was excavated from the test pits and, depending on their appearance, combined into mixed samples.
These samples were tested for polycyclic aromatic hydrocarbons (PAHs), mineral oil hydrocarbons (MOH), heavy metals and per- and polyfluorinated alkyl substances (PFAS). The results of the soil testing showed no evidence of pollution on the construction site of the sewage sludge combined heat and power plant in Walheim. The tested soil material can therefore be safely and, provided it is suitable from a geotechnical perspective, unreservedly reused in the building process.
March 2025
The new access road to the power plant is built. Pipe packages were installed for water, the fire main, district heating and electrical conduits, among other things.
February 2025
Work on the installation of 226 bored piles is under way. These stabilize the subsoil because they transfer the load from the building structures into soil layers more capable of bearing loads.
January 2025
The former coal dump was prepared for the construction of the bored piles, with excavators used to scrape off the thin layer of coal.
November 2024
Preparatory work, including cutting in an access road, started at the site after Stuttgart Regional Council’s decision of 30 October 2024 to allow the advance construction work to begin (see Stuttgart Regional Council’s press release). This allows certain preparatory work to be carried out on the site. EnBW informed the residents of Walheim and Gemmrigheim about this in writing, with the letter sent to every home on Friday, 8 November 2024.
August 2024
Stuttgart Regional Council granted approval for advance work to start on relocating sand lizards and wall lizards. The relocation measures for the sand lizards and wall lizards began on Wednesday, 21 August 2024, with the creatures professionally captured by experienced wildlife ecologists and relocated to their new habitat built on the edge of the power plant site. This work can only be carried out at certain times of the year.
February 2024
Load testing on the test piles was completed. At the beginning of 2024, load tests were performed on the test piles on the coal dump at Walheim power plant. They had been installed at a depth of around 26 meters at the end of 2023 but had to be allowed to set before testing could begin. This involves using so-called reaction piles to exert pressure on the test piles by means of a hydraulic press. The reaction piles formed the end bearing over the red steel girder. The pressure was applied slowly over different load levels and cycles, with the settlement and deflection of the test pile registered and recorded by measuring devices.
Januar 2024
In January 2024, the application documents for the planned sewage sludge combined heat and power plant in Walheim were made available for public review.
EnBW had already submitted the application for the first partial permit under immission control regulations to the responsible Stuttgart Regional Council (RPS) in February 2023. After reviewing and supplementing the documents, the RPS eventually confirmed that they were complete. On 19 January 2024, the project was announced in the “Staatsanzeiger”, on the websites of RPS and the municipalities of Walheim and Gemmrigheim, and via the central EIA portal. The announcement text can be found at www.rp-stuttgart.de > Service > Proclamations > Environmental matters.
The application documents were available for public review from 26 January to 26 February 2024, at the town halls of both municipalities and at the RPS. At the same time, documents relevant to the decision-making process were also available online on the EIA portal. Objections to the project could be raised in writing or electronically to RPS or the two municipalities until 26 March 2024. Meanwhile, RPS had asked the public authorities affected by the plans for an expert opinion on the project.
In June 2024, the corresponding discussion meeting finally took place at the Forum in Ludwigsburg to discuss the objections that had been raised.
April 2022
Using various forms of dialog – discussion panels, information visits, hotlines and digital platforms – we communicate with citizens, municipal leaders and stakeholders in the region in order to answer questions about the planned sewage sludge combined heat and power plant, share opinions and provide up-to-date information.
Ideas and change requests submitted by municipal councilors and Walheim citizens have been incorporated into the design of the new sewage sludge combined heat and power plant. As a result, it has once again been possible to significantly reduce the size of the structure.
On 26 and 29 April 2022, EnBW threw open the gates of Walheim power plant to interested Walheim residents and initiative groups, giving them the opportunity to put their questions directly to EnBW’s representatives and discuss the plans for the construction of the sewage sludge combined heat and power plant. A session organized by the local members of the state parliament with the municipal councilors of Walheim, Kirchheim a. N., Gemmrigheim and Besigheim was also used to engage people in dialogue. We are constantly incorporating suggestions and comments from the events and meetings into our existing questionnaire. Read on to find out more about Walheim’s first dialogue event.
“Everything on the table” was the motto at a dialog event involving municipal councilors and the mayors of Walheim, Besigheim, Gemmrigheim and Kirchheim am Neckar along with the “Neckar Valley Citizens” initiative. On 1 April, at the invitation of the two members of the state parliament Tobias Vogt (CDU) and Tayfun Tok (The Greens), around 60 participants came to the community center in Walheim to discuss essential aspects of the planned sewage sludge combined heat and power plant. We have posted a link to the presentation for the dialog event on this page.
The Tübingen dialog expert Dr. Antje Grobe had spoken with all participants in advance and taken their questions so that matters could be discussed on the day in four thematic blocks, including “Technology” and “Legal framework.” In the subsequent discussion, further questions from the audience were taken. Michael Class (Head of Portfolio Development) and Andreas Pick (Overall Project Manager for Fuel Switch Projects) were on hand to answer questions for EnBW. Further details were provided by Werner Maier from the German Association for Water, Wastewater and Waste and Martin Wiemann from the political entity representing the interests of the Stuttgart Region.
On behalf of EnBW, Michael Class thanked those in attendance for making the dialog event possible: “We are pleased that the format has been accepted by all sides and has equally been met with great interest. For this, we wish to thank the two members of the state parliament Tobias Vogt and Tayfun Tok, who extended the invitations to the dialog event. Particularly valuable to us were the numerous contributions to the discussion from the communities and the citizens’ initiative, which once again highlighted to us the areas where there are still unanswered questions and concerns among the citizens. We will, of course, address these issues in due course, especially since certain detailed questions can only be answered as the project progresses. For example, we are happy to work with the communities and citizens to find ways of better integrating a new plant into the landscape and reducing its visual impact. We took away many insights from the event, which we can now work on internally and hopefully discuss in further meetings the people of Walheim.”
1 January 2025
3 January 2025
29 January 2025
13 February 2025
27 February 2025
17 March 2025
27 March 2025
9 April 2025
23 April 2025
7 May 2025
21 May 2025
4 June 2025
18 June 2025
2 July 2025
16 July 2025
30 July 2025
13 August 2025
27 August 2025
3 September 2025
19 September 2025
1 October 2025
Frequently asked questions
An expert survey conducted to determine the expected construction noise during the day has shown compliance with the legal requirements of the General Administrative Regulation for Protection against Construction Noise (AVV Baulärm) in all construction phases, taking into account the noise protection measures.
During nighttime work, such as concrete finishing, the noise rating level is limited to a maximum of 47 decibels based on the A-weighted scale (dB(A)) in compliance with noise protection measures applicable to residential areas under planning law. According to current case law, no health hazard is expected from construction noise at night, even without noise protection measures.
The construction phase (building work and commissioning) will last about three years, depending on approval processes.
A comprehensive noise forecast has shown that the noise generated in the course of operating the plant complies with all legal requirements. The noise emissions are at least six decibels (dB) below the maximum limit laid down by noise control regulations (TA Lärm).
Various noise protection measures are being taken to comply with the permissible limits, including the installation of a noise barrier for the container handling zone
The plant will operate around the clock. The sewage sludge is scheduled to be delivered from Monday to Friday between 6 a.m. and 8 p.m. There will only be Saturday deliveries after public holidays – as is the case for the garbage collection, for example – or in exceptional cases.
The plant is safe because it has been designed in compliance with all legal regulations to ensure safe operation. Various expert reports consider fire, explosion and flood protection scenarios, and the system is built and operated accordingly:
- In the event of faults affecting air quality, operations at the plant are temporarily suspended. This prevents any environmental damage.
 - Fires and smoke formation are effectively prevented and safely extinguished in an emergency. A fire safety certificate confirms compliance with building regulations.
 - Explosions are also prevented. The explosion protection concept meets all legal requirements.
 
The materials and chemicals used or produced by the plant are not classified as “hazardous substances” under the Major Accidents Ordinance (StörfallVO). Following decommissioning of the coal blocks, the plant will continue to be classified as an operating area in the lower class as per the StörfallVO (it was previously classified in the upper class).
The buildings at the plant will be up to 36 meters (m) tall. Its chimney will be 50 meters tall, measured from the power plant’s new level of 180.2 meters above standard zero (“Normalnull” or N.N.).
Thanks to the use of sophisticated technology, the plant does not smell: The air needed to incinerate the sewage sludge (so-called “combustion air”) is extracted from all odorous areas of the plant, creating a vacuum. This vacuum prevents any odorous air from escaping.
The sewage sludge, meanwhile, is delivered via airlocks, for which there is also an extraction system. All of the extracted air is then fed into the incineration process, which destroys all odors. During plant downtimes – when it is being overhauled, for example – the exhaust air is cleaned using filters so that even then no odors can develop.
The operation of the sewage sludge CHP plant will generate emissions. At the same time, the decommissioning of the site’s coal blocks will eliminate all emissions previously generated by the operation of the coal blocks. As a result, fewer airborne pollutants will be released into the environment in the future.
The new plant was put out to tender in anticipation of the latest standards of the 17th Regulation on the Implementation of the Federal Immission Control Act (BImSchV), as amended in 2024, and it exceeds its requirements.
The planned plant also meets all air quality control regulations (TA Luft), precluding any harmful environmental impact and soil changes. This has been confirmed by independent expert surveys in the course of the approval process and is being reviewed by the responsible licensing authority.
Analyses performed by a specialist company have shown that the higher values recorded in a small number of places do not pose a danger to the groundwater. This assessment is based on the results of an accredited laboratory and the maximum permissible pollution levels.
A soil sample at a depth of four to five meters, taken outside the construction site and the coal storage area, detected slightly elevated heavy metal values. These probably come from foundry sands in the backfill materials. They cannot have any impact on the groundwater because a sample taken directly below the first was within normal limits when tested for heavy metal content. Groundwater was not encountered in the course of drilling.
Soil samples from the construction site were also tested. The result shows that the soil mixed with the coal dust contains more carbon, increasing the sample’s TOC (total organic carbon) content and loss on ignition value (proportion of organic and combustible substances). Since these naturally occurring substances are considered harmless, however, the presence of coal dust in the soil does not pose a problem from a toxicological perspective, although it does mean that the soil cannot be reused freely. There is thus no proof that the soil quality has been impaired as a result of coal being stored on the construction site.
The coal residue present as a result of the site’s former use as coal storage facility was removed prior to the actual excavation work and placed in heaps outside the construction site for declaration purposes.
All emissions from the plant are very clearly below the values laid down by air quality control regulations (TA Luft). Accordingly, they have no relevant impact on the wine-growing areas, the agricultural soils and the municipal areas of Walheim and Gemmrigheim. There is therefore no negative impact on humans, animals or the environment.
Most of the sewage sludge delivered to Walheim and recycled at the plant comes from municipal sewage treatment plants in northeastern Baden-Württemberg, where it is a waste product.
The wastewater produced by the exhaust vapor in the course of recycling the sewage sludge is first pretreated and then transported by truck to the sewage treatment plant in Heilbronn. As a further option, EnBW would support the construction of a pipeline for this wastewater.
Sewage sludge is already being transported today, so this is a case of rerouting traffic rather than creating additional traffic. The construction of the plant in Walheim will lead to a considerable reduction in the total mileage because sewage sludge currently has to be transported over very long distances, sometimes up to 500 km, to Lippendorf brown coal power plant near Leipzig.
Much of the sewage sludge that is set to be brought to Walheim in the future is already being transported via the B27. No noticeable increase in the volume of local traffic is therefore expected. Above all, no delivery traffic will pass through the center of Walheim. An average of 60 trucks per day will visit the power plant site to deliver the sewage sludge and take away all operating materials, particularly the wastewater produced by the exhaust vapor. You will find further information in the answer to the question about the route.
EnBW has also commissioned an independent report to examine the potential impact of the project on local transport. It looked at several traffic counts as well as official data. The findings revealed that although additional traffic is created, there is no negative impact on the traffic junctions’ ability to cope. EnBW is also prepared to talk to the municipalities about a sewer force main to Nesselwörth sewage treatment plant in order to reduce truck traffic.
Since an increase in traffic can be stressful for the affected residents, the necessary journeys and routes of the trucks were examined in a traffic report. A comparison of the estimated additional journeys with the current traffic volume has found that the additional volume is in the low single-digit percentage range and is therefore not considered significant. Most vehicles will travel along the A81 and via highways:
Traffic will not pass through Walheim itself, but will instead take the B27 and drive along Mühlstraße directly to the access road leading to the power plant site.
Traffic will also not pass through Gemmrigheim, but will instead travel along the K1625 north of the town and over the Neckar bridge.
In Kirchheim, the majority of the traffic will only travel through the southern industrial area before turning onto the B27 coming from the Neckar bridge via Max-Eyth-Straße. Only a small, unavoidable part of the traffic will use the B27 passing through the town.
The sewage sludge can currently only be delivered by truck because the sewage treatment plants that provide the sewage sludge do not have the necessary infrastructure to transport it by ship or rail. The cost of transferring the sewage sludge to ships or trains elsewhere is very high due to the small delivery radius around the plant in Walheim. EnBW is nonetheless examining the option of transporting it by rail. Alternative methods of transport are also being explored for the removal of the ashes and, if possible, other transport routes will then be used.
As operators of sewage treatment plants where sewage sludge is a waste product, municipalities throughout Germany are responsible for its disposal and are faced with the challenge of having to dispose of between seven and eight million metric tons per year.
Decentralized treatment or incineration of sewage sludge in many small plants is neither economically nor technically feasible. In Baden-Württemberg, there is not yet enough capacity to incinerate sewage sludge, which is why it currently still has to be transported over long distances. The quantities of dewatered sewage sludge and dry sludge agreed with the partner company for sewage sludge ash recycling also correspond to the sludge volume from our catchment area and reflect the actual proportion produced in municipal sewage treatment plants.
The fluidized bed incinerator technology chosen for the new plant is safe, reliable, economical and meets the current legal requirements for controlling air pollution. Compared to older systems, it also features improvements that reduce environmental pollution caused by odors and harmful emissions. These include the ability to take delivery of the sewage sludge in the building with airlocks, activated carbon filters for silo air extraction and treatment of the wastewater produced by the exhaust vapor. Alternative processes such as pyrolysis or hydrothermal carbonization have generally only been tested on a small scale. They require additional energy and are therefore less efficient, not to mention further disadvantages in terms of reliability and the usability of the ashes.
EnBW examined all its sites in northern Baden-Württemberg where planning rights exist for a power plant so that it could recycle the sewage sludge as locally as possible. Walheim proved to be the best location for the new plant:
- Since there is already a power plant on the site, it has an excellent infrastructure.
 - The site is conveniently situated, reducing unnecessary journeys to dispose of the sewage sludge.
 - Due to the impending coal phaseout, the existing power plant on the site will no longer be needed, freeing it up for a new purpose.
 - The new sewage sludge recycling plant is a sensible way of using the existing site without having to develop new land.
 
There are already well-qualified employees on the site who can operate the new plant.
EnBW concentrated its search on the northeastern part of Baden-Württemberg. There is an as yet unmet need here to recycle regional sewage sludge. Both industrial sites and existing power plants owned by EnBW were considered. The advantage here is that no new areas of land are sealed, existing infrastructure can continue to be used and investment costs are kept as low as possible. With this in mind, Marbach, Obrigheim, Heilbronn and Walheim came under consideration:
- Marbach and Obrigheim were ruled out due to a lack of space and unfavorable conditions relating to planning law as well as the staff composition and infrastructure.
 - Heilbronn didn’t have the required planning permission. Furthermore, due to a lack of space, the plant could not be completed in time for the construction of the fuel switch project (which involves replacing coal power plants with modern H2-ready combined cycle gas turbine plants).
 - Walheim was therefore chosen as the most suitable location (see question above).
 
A new building in a different location would require a higher level of investment and involve a more complex approval process – both factors that would have a negative impact on the profitability of the project. The same also goes for sites at existing sewage treatment plants because EnBW does not own any.
Stuttgart Regional Council is the approval authority.
Current calculations assume an investment in the low three-digit million range.
It is expected that around 20 posts will be needed to operate the new plant. Then there are the other posts needed to operate the existing on-site facilities, such as the gas turbine plant.
On behalf of the Federal Network Agency, EnBW was required to operate Walheim coal power plant in the so-called grid reserve until March 31, 2025. Both the Walheim 1 block and the Walheim 2 block have now been officially decommissioned since April 1, 2025.
The new plant will be housed in a building that will be specially constructed on the site of the former coal dump, which has been cleared. Due to the status of the old Block 2, which is set to remain in operation as a grid reserve power plant until the end of March 2025, the use of existing buildings is not possible for regulatory reasons.
The entire power plant site is designated in regional planning policy as a “priority area for regionally significant power plants.” Accordingly, any kind of use that conflicts with this policy is not permitted.
In addition, the gas turbine on the power plant site will continue to operate independently of the decommissioning of the coal blocks, which means that it cannot be used as residential or commercial space.
This is a sewage sludge mono-incineration plant based on fluidized bed technology, a reliable and established method for sewage sludge recycling in Germany. It is in line with the latest technological developments and is used at 23 of 29 existing plants.
The technology is also constantly evolving, which means that the planned plant in Walheim features significant improvements compared to older sewage sludge mono-incineration plants with a stationary fluidized bed. One example of an improvement is the flue gas cleaning system, which effectively reduces pollutants and comfortably meets the stricter emission limits introduced in 2024, in some cases even falling below them.
More modern methods, such as pyrolysis, have not yet been technically perfected and are highly susceptible to failure, which can compromise the safe disposal of sewage sludge. Most of them are still undergoing testing and cannot yet be scaled up.
Since energy is released during sewage sludge incineration, the plant can generate energy in the form of sufficient electricity to meet its own supply needs as well as useful heat. To this end, the plant is technically equipped with a waste heat boiler, a steam turbine and a heat extraction option. The plant generates a surplus of electricity and heat. According to the approval application, it thus meets the definition of a combined heat and power plant pursuant to the 4th and 17th Regulation on the Implementation of the Federal Immission Control Act (BImSchV).
Dewatered sewage sludge, such as that which comes from sewage treatment plants, is still a very moist fuel (approx. 75% water content) and also contains components of substances that cannot be used for energy purposes, such as sand. A large part of the energy generated is therefore used directly in the plant, especially the heat for drying the sewage sludge prior to incineration and the electricity generated to meet the plant’s own needs.
If the delivered sewage sludge meets the necessary criteria, the plant does not require any additional fuel and generates more electricity than it needs itself. This makes the planned concept in Walheim sustainable because other technologies used to recycle sewage sludge are not self-sufficient in energy terms and require fossil fuel.
Some of the heat generated is used internally to increase efficiency, while excess heat could be used externally. The plant therefore has the necessary technical setup for heat extraction, including a connecting pipeline to the property boundary. The plant can extract up to four megawatts thermal (MWth) at full load, which could be used for a local heating supply.
In Walheim, however, there is no local heating network as yet. EnBW is therefore offering support to set up such a network, which can bring further advantages as part of the legally prescribed heat planning at local authority level. EnBW already operates local heating networks nearby, which could potentially be supplied by the plant if no local heating concept can be devised in Walheim.
Municipal sewage sludge mainly comes from the waste that is flushed down the lavatory every day. It is thus a biogenic fuel and the energy generated from it (both electricity and heat) is largely carbon-neutral and therefore “green.”