Back to top Chapter-links Chapter-navigation Close Content-navigation Light Days Day Download image Go to slide [COUNT] Hours Hour Dark Main-navigation Minutes Minute Next slide Pause Play Previous slide Read Article Aloud Pause Reading Resume Reading Scroll left Scroll right Reset search input Submit search Seconds Second Share Stock exchange is momentarily closed Tab-navigation

EnBW He Dreiht offshore wind farm

Powerful energy in the North Sea without state funding

The He Dreiht wind farm (Low German for “It spins”) is located roughly 90 kilometers northwest of the island of Borkum and 110 kilometers west of Helgoland. It is our third offshore wind farm in the North Sea and by far the largest: 64 wind turbines with an installed output of 960 megawatts (MW) can supply the equivalent of more than one million households with renewable energy for an entire year. This makes He Dreiht Germany’s largest offshore wind farm to date.

In focus
Milestone reached: He Dreiht is complete!

The He Dreiht offshore wind farm has been fully built, with all 64 wind turbines now installed, giving us reason to celebrate. That is exactly what we did on 17 September 2026 at the official inauguration ceremony – together with guests from the political sphere, business world and wider society, including Carsten Schneider, Federal Minister for the Environment, Climate Action, Nature Conservation and Nuclear Safety. After all, He Dreiht isn’t just any old wind farm – it is one of the most important projects for being able to supply Germany with renewable electricity.

Link to the press release

Show video
Show YouTube video?

Please note the privacy policy of YouTube.

The latest news on offshore wind

Project details

An overview of the He Dreiht North Sea wind farm

A map of the area around He Dreiht

The He Dreiht wind farm is located in the middle of the North Sea – about 85 kilometers northwest of Borkum and 110 kilometers west of Helgoland – not far from our North Sea wind farms EnBW Hohe See and Albatros.

In terms of its construction, however, He Dreiht is on a completely new scale, with 64 Vestas V236-15.0 MW wind turbines, each boasting a capacity of 15 MW, being used for the first time. The turbines boast a hub height of 142 meters and a rotor diameter of 236 meters. One rotation of these giants is enough to supply the equivalent of four households with electricity for a day. In total, the farm can supply the equivalent of 1.1 million households with electricity for an entire year.

Offshore wind farm with no state funding

Back in 2017, we were awarded the contract for He Dreiht in the first round of auctions for offshore wind farms in Germany, with no entitlement to state funding. We secured long-term financing of 600 million euros for the major project – which is costing in the region of 2.4 billion euros – from the European Investment Bank, one of the world’s largest financial backers of climate change mitigation and environmental projects. In addition, a minority shareholding of 49.9 percent was awarded to a consortium consisting of Allianz Capital Partners on behalf of Allianz companies, AIP and Norges Bank.

We are also marketing the electricity through long-term power purchase agreements (PPAs). Corresponding purchase agreements have already been signed with partners such as the operating company of Frankfurt Airport (Fraport), Evonik, Salzgitter, Bosch, Deutsche Bahn, Telekom subsidiary PASM, SHS-Stahl-Holding Saar and Google.

Natural and environmental concerns considered

When planning and building an offshore wind farm, we are aware of our particular duty toward the environment and nature, and we tailor our projects accordingly. This is especially important in a sensitive habitat like the German North Sea. An environmental impact assessment was therefore carried out as part of the approval process for the He Dreiht offshore wind farm. An easy-to-understand, non-technical summary of the findings can be found here (only available in German).

He Dreiht: Technical Data

Installed output
960 MW
Annual yield
3.6 billion kWh
Turbines
64 Vestas V236-15.0 MW
Foundations
Monopiles
Hub height
142 meters
Rotor diameter
236 meters
Swept area
43,742 square meters = roughly 6 football fields
Average wind speed
10,4 m/s
Water depth
37.7–40.6 meters

A Comparison of EnBW's Offshore Wind Farms

Source: EnBW; State: 09 / 2026
Construction diary
He Dreiht: Germany’s largest offshore project is taking shape

Construction work got underway on He Dreiht, Germany’s largest offshore wind farm, in May 2024. At peak times, more than 500 people worked on this large construction site in the middle of the sea. Over 60 vessels were involved. A look back in pictures.

Components from throughout Europe

Besides being one of the largest offshore projects in Europe, many of the components for He Dreiht were manufactured in various locations between Great Britain and Italy.

The components for He Dreiht are produced in various countries. The project is being managed from Hamburg, while the service station is based in Emden. Source: EnBW

Grid connection: 120 kilometers to the coast via submarine cables

Kilometers of submarine cables, a converter platform and high-voltage DC cables to the mainland – the process of connecting the He Dreiht offshore wind farm to the grid was a mammoth task from a technical, logistical and organizational perspective. The Dutch-German grid operator TenneT connected the wind farm to the grid using an offshore converter station and two high-voltage DC export cables. It involved laying 120 kilometers of cable under water and a further 110 kilometers on land.

Media library

Find out more about the megaproject and the team

From the beginnings to the completion

We were awarded the contract for “He Dreiht” in April 2017. Nine years later, Germany’s largest offshore wind farm is now complete. In the video, we show its history and present the people who made the project possible.

Behind the scenes

How are marine mammals actually protected on such a large offshore construction site? And what do the colleagues do on board once they have finished their shift? Who would have thought, for instance, that there would be a swimming pool on the giant crane vessel?

The foundations are laid

In mid-May, the first of the 64 foundations for what is currently the largest offshore wind farm was laid in the middle of the night. The rising sun then greeted the team early in the morning.

One of the largest crane vessels in the world – the “Thialf”

The giant crane ship and the “largest hammer in the world” – images of the construction work for the He Dreiht offshore wind farm. EnBW colleagues Michael and Jan are aboard the “Thialf” to lay the foundations for the wind turbines.